Wapening uittrekken en buigstaat (Verenigde Arabische Emiraten, BS 8666)
You are the builder's quantity surveyor on a five-storey block of flats in the UAE: you measure the work and price it. This course is about rebar, the steel bars inside the concrete. In five tasks you take the bars from the beam and slab drawings to a priced package in the bill, then value the drawing revision that changes the bar sizes.
Fictief project- Building
- Ground plus four floors, concrete frame, flat slabs
- Contract
- FIDIC Red Book 2017 (international standard contract), with a bill of quantities, in AED
- Story
- March 2026 (Revision B) to June 2026 (Revision C)
- Werk in de ERP
- 5 opdrachten, ongeveer 3 u 40 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
EngineerIssues drawings and instructions- Beam B7 detail, Rev BOpdracht 1
- Slab S3 detail, Rev BOpdracht 2
- Instruction EI 07, Rev COpdracht 5
Steel supplierQuotes and delivers the steel- Quotation per tonneOpdracht 4
UQuantity surveyor, main contractorGaat van u uit
- Measured bill linesOpdracht 1
- Package priceOpdracht 4
- Variation orderOpdracht 5
- Order quantity, waste inOpdracht 3
Het project en de mensen zijn fictief. De portretten zijn gegenereerd.
Uw route door het project
Two tasks measure, one weighs, one prices, one values a change. Start with task 1: in the Bill of Quantities you work out the total length of each bar in beam B7.
Measure
Opdracht 1 · 45 min
Balk B7: staven volgens vormcode
- U levert
- Total length of each beam bar mark (each bar type on the drawing)
- Document
- Beam B7 detail, Revision B
- In de ERP
- Bill of Quantities
Measure
Opdracht 2 · 45 min
Vloer S3: staven, overlappen en netten
- U levert
- Slab bars with laps (overlaps at joints), and mesh sheets
- Document
- Slab S3 detail, Revision B
- In de ERP
- Bill of Quantities
Weigh
Opdracht 3 · 40 min
Gewichten, tonnage en de bestelling
- U levert
- Net tonnes by bar size, and the order
- Document
- Mass per metre, element counts
- In de ERP
- Bill of Quantities
Price
Opdracht 4 · 40 min
Prijs het wapeningspakket
- U levert
- A rate per net tonne, and the package price
- Document
- Supplier quotation and labour rates
- In de ERP
- Bill of Quantities, Markups
Change
Opdracht 5 · 50 min
Revisie C: herbereken de wijziging
- U levert
- The variation (priced change) for the new bar sizes
- Document
- Engineer's instruction EI 07, Revision C
- In de ERP
- Variations
How a drawing becomes a price
Each step below is one task, in the order the steel moves. Task 3 sits between the slab and the price: it turns metres into net tonnes, and keeps the waste for the order.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Measure the bar that is bent, not the box around it. Bill net tonnes. Put the waste in the order and the supply price, the markup in one row.