OpenConstruction Academy
เข้าสู่ระบบ / สมัครสมาชิก
TH

ทฤษฎีก่อนงานที่ 5 · 9 นาที

Pricing unsuitable ground

วัสดุไม่เหมาะสม: การปรับเปลี่ยนราคา

หลังจบบทเรียนนี้ คุณจะสามารถ

  1. Measure the unsuitable material by average end area, in bank m³.
  2. Price its removal per bank m³ and the granular backfill per tonne.
  3. Enter the change without HST, which belongs on the invoice.
1 / 5

Ground that is not what the drawings showed

Test pits below the road find soft, organic silt that cannot carry it. The engineer orders it dug out and replaced with granular fill. The work was not in the bill, so it is a change to the contract: measured, priced at rates agreed with the engineer, and approved before it is paid.

ตัวอย่าง. In OpenConstructionERP a change goes through «Variations»: a request with its estimated cost impact, approval, then an order.
2 / 5

Measure the hole

The engineer gives the area of silt to remove at each test pit section. Measure it like any cut: each segment's length times the mean of its two end areas, in bank m³. Every section counts, including the ones in the middle.

ตัวอย่าง. Using one average area for the whole length, or only the end sections, gives a different volume from the one the engineer will check.
3 / 5

Out: per bank m³

Removal is excavation, haul and disposal. The haul rate is per bank m³. A licensed site for organic soil charges its gate fee per loose m³, so each bank m³ costs one plus the swell times that fee. Ordinary clean-fill rates do not apply: silt goes to a site that accepts it.

ตัวอย่าง. With a haul rate of $9.00 and a fee of $15.00 per loose m³, removal costs 27.75 dollars per bank m³.
$9.00$18.75
  • Haul rate per bank m³ $9.00
  • Gate fee per bank m³, swell 25% $18.75
4 / 5

In: per tonne

Granular B is bought and paid by weight. The hole is backfilled to its own volume, compacted, so the compacted volume equals the bank volume removed. Multiply by the compacted density to get tonnes, then by the rate per tonne. No shrinkage conversion: the hole is filled, not built up from loose soil.

ตัวอย่าง. 100 m³ of hole at 2.2 tonnes per m³ takes 220 tonnes of Granular B.
5 / 5

HST stays off the change

Ontario HST is 13%: 5% federal and 8% provincial. It is charged on the invoice when the work is billed, not built into the value of a change. Enter the net value in the request.

ตัวอย่าง. A change worth 18,000 dollars is entered as 18,000 dollars. The 2,340 dollars of HST appears on the invoice.

Price a smaller pocket of silt

Different sections and rates from your task. Predict each figure first.

ไม่ได้วาดตามมาตราส่วน
โจทย์
  • Silt to remove at 0+200 5.00 m², 0+225 8.00 m², 0+250 6.00 m².
  • Haul rate $9.00 per bank m³. Licensed site fee $15.00 per loose m³. Swell 0.25.
  • Granular B $35.00 per tonne, placed and compacted, at 2.2 tonnes per m³. Rates exclude HST.
162.5175
  • 0+200 to 0+225 162.5
  • 0+225 to 0+250 175
162.5175
  • 0+200 to 0+225 162.5
  • 0+225 to 0+250 175
ขั้นตอนที่ 1 จาก 4

Volume of silt

Two segments of 25 m. How many m³ bank?

25 × (5.00 m² + 8.00 m²) ÷ 2 + 25 × (8.00 m² + 6.00 m²) ÷ 2 = 337.5 m³ bank.

Rate per bank m³?
Volume, bank m³337.5
Removal?
Rate per bank m³$27.75
Volume, bank m³337.5
Removal$9,365.62
ขั้นตอนที่ 2 จาก 4

Taking it out

Haul rate plus the gate fee in bank m³, times the volume. Give cents.

$9.00 + $15.00 × 1.25 = $27.75 per bank m³. × 337.5 = $9,365.62.

Hole, m³ compacted337.5
Tonnes per m³2.2
Tonnes?
Hole, m³ compacted337.5
Tonnes per m³2.2
Tonnes742.5
ขั้นตอนที่ 3 จาก 4

Tonnes of Granular B

The hole is filled to its own volume, compacted. How many tonnes?

337.5 × 2.2 = 742.5 tonnes.

+$9,3661?2?3
  • 1 Removal
  • 2 Granular B
  • 3 Change, without HST
+$9,3661+$25,9882$35,3533
  • 1 Removal
  • 2 Granular B
  • 3 Change, without HST
ขั้นตอนที่ 4 จาก 4

Value of the change

Removal plus backfill, without HST. Give cents.

Backfill 742.5 t × $35.00 = $25,987.50. Change $9,365.62 + $25,987.50 = $35,353.12, net of HST.

สรุปสั้น ๆ. Measure in bank m³, price removal per bank m³ with the fee converted, price backfill by the tonne at the hole's own volume, and leave HST for the invoice.

ทดสอบตัวเอง

คำถามที่ 1 จาก 3

A hole of 100 m³ is backfilled with Granular B at 2.2 tonnes per m³ compacted, priced at $36.00 per tonne. What is the backfill worth?

100 × 2.2 = 220 tonnes. × $36.00 = $7,920.00.
คำถามที่ 2 จาก 3

The change is worth $18,000.00 before tax. What goes into «Estimated cost impact»?

  • The change value is net. HST is added on the invoice.

  • Tax is charged when the work is invoiced, not built into the change.

  • Neither part of HST belongs in the change value.

คำถามที่ 3 จาก 3

Which rate applies to removing organic silt?

  • That rate includes a clean-fill tip. Silt goes to a licensed site at its own fee.

  • That is the rate agreed for this change.

  • That prices the backfill, the other half of the change.