بل کو پرائس کریں اور ٹریڈ کی تاریخ تک ویلیو نکالیں
اس لیکچر کے بعد آپ کر سکیں گے
Price a bill line as quantity times rate, with the rate and the quantity in the same unit.
Add every section of a remeasured trade to get its value to date.
Test a draft claim against the remeasured value, not against a percentage or a cost report.
1 / 3
Quantity times rate, in the rate's unit
Each line in the priced bill has a fixed rate per unit: per m³, per m², per m or per t. The line total is the quantity times that rate. Read the unit before you multiply. Reinforcement is priced per tonne, so a quantity typed in kilograms gives a figure a thousand times too big.
مثال. A line that comes out in millions on a two-storey job is almost always kilograms against a rate per tonne.
Reinforcement, t12.4
Rate per t$2,390.00
Line total$29,636.00
2 / 3
The trade to date is every section
A remeasured trade grows section by section: footings and slab on ground first, then columns, then each suspended slab. Its value to date is the sum of all sections at bill rates, not this month's section alone. The quantities are the net ones from the measurement, never the gross outline.
مثال. On another job: section 1 $26,480.50, section 2 $71,240.00, section 3 $158,906.20.
$71,240$158,906
Section 1, footings $26,480
Section 2, columns $71,240
Section 3, this month's slab $158,906
3 / 3
A percentage by eye is not a measure
On a lump sum contract with a priced bill, most trades in the schedule of values are assessed as a percentage complete. A trade the contract says is remeasured is valued at bill rates instead. A draft that gives it the same percentage as the others is a guess. The site cost report is not a basis of payment either: it shows what the work cost you, not what the contract pays for it.
مثال. If the draft is higher than the remeasure, the difference is an overclaim that the Superintendent will cut, with your credibility.
Draft: 40 % of a $690,000 trade
$276,000
Remeasured at bill rates
$256,627
Value a remeasured trade
Another job, a car park deck. Section 1 is priced. Price section 2 and test the draft claim.
پیمانے کے مطابق نہیں
مسئلہ
Section 1 to date: $31,872.40. Section 3 to date: $186,420.75.
Section 2: concrete 48.2 m³ at $398.00; column formwork 512.4 m² at $112.50; reinforcement 11.35 t at $2,410.00 per t.
Draft claim: 43% of the trade's contract value $840,000.
Reinforcement, t11.35
Rate per t$2,410.00
Line total?
Reinforcement, t11.35
Rate per t$2,410.00
Line total$27,353.50
مرحلہ 1 از 4
Reinforcement line
Price the reinforcement line of section 2. Quantity and rate are both per tonne.
اشارہ: Tonnes times the rate per tonne.
11.35 t × $2,410.00 = $27,353.50.
$19,184$57,645$27,354
Concrete $19,184
Formwork $57,645
Reinforcement $27,354
$19,184$57,645$27,354
Concrete $19,184
Formwork $57,645
Reinforcement $27,354
مرحلہ 2 از 4
Section 2 total
Add the concrete and formwork lines. What is the section 2 total?
اشارہ: Three lines, each its quantity times its rate.