OpenConstruction Academy
התחברות / הרשמה
HE

תיאוריה לפני משימה 2 · 10 דק׳

Pricing a remeasured trade at the bill rates

תמחרו את כתב הכמויות והעריכו את המקצוע עד כה

אחרי ההרצאה הזו תוכלו

  1. Price a bill line as quantity times rate, with the rate and the quantity in the same unit.
  2. Add every section of a remeasured trade to get its value to date.
  3. Test a draft claim against the remeasured value, not against a percentage or a cost report.
1 / 3

Quantity times rate, in the rate's unit

Each line in the priced bill has a fixed rate per unit: per m³, per m², per m or per t. The line total is the quantity times that rate. Read the unit before you multiply. Reinforcement is priced per tonne, so a quantity typed in kilograms gives a figure a thousand times too big.

דוגמה. A line that comes out in millions on a two-storey job is almost always kilograms against a rate per tonne.
Reinforcement, t12.4
Rate per t$2,390.00
Line total$29,636.00
2 / 3

The trade to date is every section

A remeasured trade grows section by section: footings and slab on ground first, then columns, then each suspended slab. Its value to date is the sum of all sections at bill rates, not this month's section alone. The quantities are the net ones from the measurement, never the gross outline.

דוגמה. On another job: section 1 $26,480.50, section 2 $71,240.00, section 3 $158,906.20.
$71,240$158,906
  • Section 1, footings $26,480
  • Section 2, columns $71,240
  • Section 3, this month's slab $158,906
3 / 3

A percentage by eye is not a measure

On a lump sum contract with a priced bill, most trades in the schedule of values are assessed as a percentage complete. A trade the contract says is remeasured is valued at bill rates instead. A draft that gives it the same percentage as the others is a guess. The site cost report is not a basis of payment either: it shows what the work cost you, not what the contract pays for it.

דוגמה. If the draft is higher than the remeasure, the difference is an overclaim that the Superintendent will cut, with your credibility.
Draft: 40 % of a $690,000 trade
$276,000
Remeasured at bill rates
$256,627

Value a remeasured trade

Another job, a car park deck. Section 1 is priced. Price section 2 and test the draft claim.

לא בקנה מידה
הבעיה
  • Section 1 to date: $31,872.40. Section 3 to date: $186,420.75.
  • Section 2: concrete 48.2 m³ at $398.00; column formwork 512.4 m² at $112.50; reinforcement 11.35 t at $2,410.00 per t.
  • Draft claim: 43% of the trade's contract value $840,000.
Reinforcement, t11.35
Rate per t$2,410.00
Line total?
Reinforcement, t11.35
Rate per t$2,410.00
Line total$27,353.50
שלב 1 מתוך 4

Reinforcement line

Price the reinforcement line of section 2. Quantity and rate are both per tonne.

11.35 t × $2,410.00 = $27,353.50.

$19,184$57,645$27,354
  • Concrete $19,184
  • Formwork $57,645
  • Reinforcement $27,354
$19,184$57,645$27,354
  • Concrete $19,184
  • Formwork $57,645
  • Reinforcement $27,354
שלב 2 מתוך 4

Section 2 total

Add the concrete and formwork lines. What is the section 2 total?

Concrete $19,183.60, formwork $57,645.00, reinforcement $27,353.50. Section 2 $104,182.10.

$104,182$186,421
  • Section 1 $31,872
  • Section 2 $104,182
  • Section 3 $186,421
$104,182$186,421
  • Section 1 $31,872
  • Section 2 $104,182
  • Section 3 $186,421
שלב 3 מתוך 4

Trade to date

Add all three sections. What is the trade worth to date?

$31,872.40 + $104,182.10 + $186,420.75 = $322,475.25.

Draft
$361,200
Remeasured
$322,475
Draft
$361,200
Remeasured
$322,475
שלב 4 מתוך 4

What the draft overstates

The draft takes a percentage of the contract value. By how much does it exceed the remeasured value?

The draft is $361,200.00. Remeasured, the trade is worth $322,475.25. The draft overstates it by $38,724.75.

בקצרה. Price each line in its own unit, add every section, and let the remeasure, not a percentage, set the claim.

בדקו את עצמכם

שאלה 1 מתוך 3

A reinforcement line comes out at several million dollars on a small job. What is the likely cause?

  • A rate per tonne times a mass in kilograms is a thousand times too big.

  • The grade changes the concrete rate, not the steel line.

  • Laps are in the rate. Adding them would make the line bigger, not smaller.

  • Bill lines are excluding GST. GST would not explain a factor of a thousand.

שאלה 2 מתוך 3

The site cost report shows less spent on a remeasured trade than the bill values it at. What do you claim?

  • Cost is your business. The contract pays bill rates for measured work.

  • The bill is the basis of payment for a remeasured trade.

  • There is no rule for an average. Claim what the contract pays.

  • A remeasured trade is not assessed by eye.

שאלה 3 מתוך 3

Concrete 14.60 m³ at $340.00, soffit formwork 220.50 m² at $88.00, reinforcement 3.20 t at $2,450.00 per t. What is the section total?

$4,964.00 + $19,404.00 + $7,840.00 = $32,208.00.