OpenConstruction Academy
Kirjaudu / Rekisteröidy
FI

Teoria ennen tehtävää 5 · 10 min

The final invoice and the Haftrücklass

Loppulasku ja takuupidätys (Haftrücklass)

Tämän luennon jälkeen osaat

  1. Build the final invoice: contract work as built plus agreed claims.
  2. Withhold the Haftrücklass of 2 % of the net final amount for the warranty period.
  3. Compute the balance after interim payments, and know the three-month rule for reservations.
1 / 3

The final invoice settles the account

After handover (Übernahme) the contractor submits the final invoice (Schlussrechnung): all work as built at contract prices plus every agreed claim. The Deckungsrücklass of the interim invoices is released, because the account is now exact. What was paid on account is deducted.

Esimerkki. The interim payment was already net of its Deckungsrücklass, so deducting the payment made releases that Rücklass automatically.
2 / 3

The Haftrücklass

A new retention takes its place: the Haftrücklass, security for defects that appear during the warranty period. This contract sets 2 % of the net final amount, the ÖNORM B 2110 figure; some public clients' own conditions set more. It is released when the warranty period ends; for building work the statutory period is three years (ABGB § 933).

Esimerkki. Net final amount 186,755.20 €: Haftrücklass 3,735.10 €.
Net final amount€186,755.20
Haftrücklass 2 %€3,735.10
3 / 3

Accept with care

If the client cuts the final payment, the contractor has three months to reserve its rights in writing (ÖNORM B 2110, 8.4.2). Accepting a reduced final payment without that reservation closes the account.

Esimerkki. Balance = net final × 1.20 − interim payments − Haftrücklass.

Final invoice of a small extension

Handover is done. All quantities were built as tendered; one claim was agreed in full.

Ei mittakaavassa
Tehtävä
  • Contract sum net, quantities as built: €180,400.00. Agreed claim net: €6,355.20.
  • Interim invoice 1 paid: €96,887.50 (already net of its Deckungsrücklass).
  • Haftrücklass 2 % of the net final amount. USt 20 %.
Vaihe 1/3

Net final amount

Contract work plus the agreed claim. What is the net final amount?

€180,400.00 + €6,355.20 = €186,755.20.

Vaihe 2/3

Haftrücklass

2 % of the net final amount, rounded. What is withheld?

€186,755.20 × 2 % = €3,735.10.

€224,1061−€96,8882−€3,7353?4
  • 1 Gross final
  • 2 Interim paid
  • 3 Haftrücklass
  • 4 Balance
€224,1061−€96,8882−€3,7353€123,4844
  • 1 Gross final
  • 2 Interim paid
  • 3 Haftrücklass
  • 4 Balance
Vaihe 3/3

Balance paid

Gross with USt, less the interim payment, less the Haftrücklass. What is paid now?

€186,755.20 × 1.20 − €96,887.50 − €3,735.10 = €123,483.64.

Lyhyesti. The final invoice replaces the interim ones: everything built plus agreed claims, with USt, less what was paid, less the Haftrücklass.

Testaa itsesi

Kysymys 1/3

Net final amount 150,000.00 €. Interim payments made 100,000.00 €. Haftrücklass 2 % of net, USt 20 %. What is the balance paid?

180,000.00 − 100,000.00 − 3,000.00 = €77,000.00.
Kysymys 2/3

When is the Haftrücklass released?

  • The final invoice is when it is withheld.

  • Right.

  • It does not exist before the final invoice.

Kysymys 3/3

The client pays the final invoice short. What must the contractor do to keep its claim?

  • Accepting without reservation closes the account.

  • Right. ÖNORM B 2110, 8.4.2.

  • Interim invoices end with the final invoice.