Završna situacija i zadržani iznos za jamstveni rok
Nakon ovog predavanja moći ćete
Build the final invoice: contract work as built plus agreed claims.
Withhold the Haftrücklass of 2 % of the net final amount for the warranty period.
Compute the balance after interim payments, and know the three-month rule for reservations.
1 / 3
The final invoice settles the account
After handover (Übernahme) the contractor submits the final invoice (Schlussrechnung): all work as built at contract prices plus every agreed claim. The Deckungsrücklass of the interim invoices is released, because the account is now exact. What was paid on account is deducted.
Primjer. The interim payment was already net of its Deckungsrücklass, so deducting the payment made releases that Rücklass automatically.
2 / 3
The Haftrücklass
A new retention takes its place: the Haftrücklass, security for defects that appear during the warranty period. This contract sets 2 % of the net final amount, the ÖNORM B 2110 figure; some public clients' own conditions set more. It is released when the warranty period ends; for building work the statutory period is three years (ABGB § 933).
Primjer. Net final amount 186,755.20 €: Haftrücklass 3,735.10 €.
Net final amount€186,755.20
Haftrücklass 2 %€3,735.10
3 / 3
Accept with care
If the client cuts the final payment, the contractor has three months to reserve its rights in writing (ÖNORM B 2110, 8.4.2). Accepting a reduced final payment without that reservation closes the account.
Primjer. Balance = net final × 1.20 − interim payments − Haftrücklass.
Final invoice of a small extension
Handover is done. All quantities were built as tendered; one claim was agreed in full.
Nije u mjerilu
Zadatak
Contract sum net, quantities as built: €180,400.00. Agreed claim net: €6,355.20.
Interim invoice 1 paid: €96,887.50 (already net of its Deckungsrücklass).
Haftrücklass 2 % of the net final amount. USt 20 %.
Korak 1 od 3
Net final amount
Contract work plus the agreed claim. What is the net final amount?
Savjet: Two numbers.
€180,400.00 + €6,355.20 = €186,755.20.
Korak 2 od 3
Haftrücklass
2 % of the net final amount, rounded. What is withheld?
Savjet: Net × 2 %.
€186,755.20 × 2 % = €3,735.10.
1 Gross final
2 Interim paid
3 Haftrücklass
4 Balance
1 Gross final
2 Interim paid
3 Haftrücklass
4 Balance
Korak 3 od 3
Balance paid
Gross with USt, less the interim payment, less the Haftrücklass. What is paid now?