2 / 3Each deduction has its own base
Several amounts are withheld from the payment, each on its own base (matrah). Income tax withholding of 5 % applies to progress payments on construction work spanning more than one year (Income Tax Law 193, article 94), on the amount without KDV. Stamp duty is 9.48 per thousand (Stamp Duty Law 488), here on the amount without KDV. KDV withholding of 4/10 applies to the KDV itself: the administration pays that part straight to the tax office. The additional guarantee of 6 % is taken on the price adjustment, not on the work (Law 4735, article 12).
Halimbawa. Putting every rate on the same base is the classic error, and it moves the payment by thousands.
Income tax 5 % of the amount₺21,075.50
Stamp duty 9.48 ‰ of the amount₺3,995.91
KDV withholding 4/10 of the KDV₺33,720.80
Additional guarantee 6 % of F₺1,290.60
Deductions₺60,082.81