OpenConstruction Academy
Кирүү / Катталуу
KY

5-тапшырма алдындагы теория · 10 мүн

From hakediş amount to payment: KDV, withholdings and deductions

2-тастыктама: КНС, салыктар жана чегерүүлөр

Бул лекциядан кийин сиз төмөнкүнү үйрөнөсүз

  1. Add KDV at 20 % to the hakediş amount of the period.
  2. Take each deduction from its own base: income tax and stamp duty on the amount, KDV withholding on the KDV, additional guarantee on F.
  3. Compute the amount paid to the contractor.
1 / 3

The hakediş amount and its KDV

The amount of a period is the work done at contract prices plus the price adjustment F. KDV at 20 % is charged on it. Under the General Specification for Works (Yapım İşleri Genel Şartnamesi, article 39) the hakediş is cumulative, and KDV is computed on this period's amount: the cumulative amount less the previous one.

Мисал. Work 400,000.00 + F 21,510.00 = 421,510.00; KDV 20 % = 84,302.00.
2 / 3

Each deduction has its own base

Several amounts are withheld from the payment, each on its own base (matrah). Income tax withholding of 5 % applies to progress payments on construction work spanning more than one year (Income Tax Law 193, article 94), on the amount without KDV. Stamp duty is 9.48 per thousand (Stamp Duty Law 488), here on the amount without KDV. KDV withholding of 4/10 applies to the KDV itself: the administration pays that part straight to the tax office. The additional guarantee of 6 % is taken on the price adjustment, not on the work (Law 4735, article 12).

Мисал. Putting every rate on the same base is the classic error, and it moves the payment by thousands.
Income tax 5 % of the amount₺21,075.50
Stamp duty 9.48 ‰ of the amount₺3,995.91
KDV withholding 4/10 of the KDV₺33,720.80
Additional guarantee 6 % of F₺1,290.60
Deductions₺60,082.81
3 / 3

What the contractor receives

Paid = amount + KDV − deductions. Advances and delay penalties, when there are any, are further deductions with their own rules; this course has neither.

Мисал. The withheld KDV is not lost to the contractor's books; it is paid to the tax office by the administration on its behalf.

Close a hakediş

This period: work 400,000.00 at contract prices, price adjustment 21,510.00. No advance, no penalty.

Масштабсыз
Маселе
  • Work of the period ₺400,000.00; price adjustment F ₺21,510.00.
  • KDV 20 %; income tax withholding 5 %; stamp duty 9.48 per thousand; KDV withholding 4/10; additional guarantee 6 % of F.
3 кадамдын 1-си

KDV

Amount = work + F. What is the KDV?

(₺400,000.00 + ₺21,510.00) × 20 % = ₺84,302.00.

₺21,076₺33,721
  • Income tax ₺21,076
  • Stamp duty ₺3,996
  • KDV withholding ₺33,721
  • Guarantee ₺1,291
₺21,076₺33,721
  • Income tax ₺21,076
  • Stamp duty ₺3,996
  • KDV withholding ₺33,721
  • Guarantee ₺1,291
3 кадамдын 2-си

Deductions

Each on its own base. What do the deductions total?

₺21,075.50 + ₺3,995.91 + ₺33,720.80 + ₺1,290.60 = ₺60,082.81.

₺421,5101+₺84,3022−₺60,0833?4
  • 1 Amount
  • 2 KDV
  • 3 Deductions
  • 4 Paid
₺421,5101+₺84,3022−₺60,0833₺445,7294
  • 1 Amount
  • 2 KDV
  • 3 Deductions
  • 4 Paid
3 кадамдын 3-си

Paid to the contractor

Amount + KDV − deductions. What is paid?

₺400,000.00 + ₺21,510.00 + ₺84,302.00 − ₺60,082.81 = ₺445,729.19.

Кыскача. KDV on the amount, then each deduction on its own base, then pay the rest.

Өзүңүздү текшериңиз

3 суроонун 1-си

A hakediş amount is 200,000.00 without KDV. KDV is 20 % and 4/10 of it is withheld. How much KDV is withheld?

200,000.00 × 20 % = 40,000.00 KDV; 4/10 of it = ₺16,000.00.
3 суроонун 2-си

On what base is the 6 % additional guarantee taken?

  • It secures the price adjustment only.

  • Right. Law 4735, article 12.

  • KDV has its own withholding.

3 суроонун 3-си

Why is income tax withheld from a hakediş at all?

  • Only certain payments are; here it is the multi-year construction rule.

  • Right. Income Tax Law 193, article 94.

  • KDV and income tax are separate.