Measure only the extra work a direction adds, not the work the bill already pays for.
Choose between a bill rate and an agreed rate for each component.
Add the Annexure margin once, and keep GST out of the variation.
1 / 3
Value the difference, not the whole
When the Superintendent directs a thicker slab over part of a floor, the slab depth in the bill is already measured and paid. The variation is the extra: the thickened area times the depth added. The same goes for reinforcement: only the bar schedule addendum, not the whole schedule again.
Halimbawa. Measuring the whole 260 mm depth would pay the first 200 mm twice.
Thickened area, 6.00 × 4.5027.00 m²
Depth added, 200 to 260 mm, m0.06
Extra concrete, m³1.62
2 / 3
Bill rate or agreed rate
AS 4000 values a variation in an order of preference: a price agreed beforehand, then the contract's own rates where they apply, then reasonable rates. A bill rate applies only where the work is of the same kind and done under the same conditions. Concrete and reinforcement in a thickening are the same work as in the slab. A 50 mm step in the soffit is not a full-height slab edge, so the edge formwork rate does not fit it, and a rate is agreed instead.
Halimbawa. Write down why each rate was chosen. The Superintendent will ask, and the answer is the line in the bill or the agreement.
3 / 3
Margin once, GST not at all
The Annexure may set a margin for off-site overheads and profit on a variation. It goes on once, on the total of the components. GST is not part of a variation's value: variations, like bill lines, are excluding GST. The tax is added once, at the foot of the payment claim.
Halimbawa. Margin 12 % of $2,100.00 is $252.00. The 12 % is that contract's Annexure choice, not a law.
1 Concrete at the bill rate
2 Reinforcement at the bill rate
3 Formwork and trimming, agreed rates
4 Margin, 12 %
5 Variation value
Price a slab thickening
Another job: a plant room floor thickened under a directed change.
Hindi ayon sa sukat
Ang problema
Area thickened 6.4 m × 4.5 m, from 200 to 250 mm: 0.05 m added.
Bill rates: concrete $305.00 per m³, reinforcement $2,410.00 per t. Bar schedule addendum 360 kg.
Agreed rates: step formwork $35.20 per m round the thickened area; $76.00 for each of 4 new penetrations.
Annexure margin 12%.
Thickened area, m²28.8
Depth added, m0.05
Extra concrete, m³?
Thickened area, m²28.8
Depth added, m0.05
Extra concrete, m³1.44
Hakbang 1 ng 4
Extra concrete
Thickened area times the depth added. How many m³?
Pahiwatig: Only the extra depth, not the full slab.
6.4 m × 4.5 m × 0.05 m = 1.44 m³.
Hakbang 2 ng 4
Components at bill rates
Concrete and reinforcement at the bill rates. What do the two come to?
Pahiwatig: Reinforcement: kilograms to tonnes first.
Concrete 1.44 m³ × $305.00 = $439.20. Reinforcement 360 kg is 0.36 t × $2,410.00 = $867.60. Together $1,306.80.
$1,307$767
Bill rates $1,307
Step formwork $767
Penetrations $304
$1,307$767
Bill rates $1,307
Step formwork $767
Penetrations $304
Hakbang 3 ng 4
Before the margin
Add the step formwork and the penetrations at the agreed rates. What is the variation before the margin?
Pahiwatig: The step runs round the thickened area: its girth.
Girth 21.8 m × $35.20 = $767.36. Penetrations 4 × $76.00 = $304.00. With $1,306.80 that is $2,378.16.
1 Before the margin
2 Margin
3 Variation value
1 Before the margin
2 Margin
3 Variation value
Hakbang 4 ng 4
Variation value
Add the Annexure margin. What is the value of the variation, excluding GST?
Pahiwatig: Margin once, on the total. No GST.
$2,378.16 plus 12% is $2,663.54, excluding GST.
Sa madaling salita. Measure the extra only. Bill rates where the work is the same, agreed rates where it is not. Margin once, GST later.
Subukin ang sarili
Tanong 1 ng 3
A direction adds a 50 mm soffit step. The bill has edge formwork at 250 mm high. Which rate do you use?
The height is part of the description. A different height is different work.
Where no contract rate applies, a rate is agreed or a reasonable rate is used.
Formwork is a measured item in this bill.
Scaling is a way to reach an agreed rate, not the bill rate itself.
Tanong 2 ng 3
Where does GST go when you price a variation?
Variations are excluding GST, like the bill.
That still puts it in the variation.
The tax follows the claim, not each line.
Construction work is a taxable supply. The tax is added on the claim.
Tanong 3 ng 3
Components at bill and agreed rates total $5,240.00. The Annexure margin is 8 %. What is the variation value, excluding GST?