Measure only the extra work a direction adds, not the work the bill already pays for.
Choose between a bill rate and an agreed rate for each component.
Add the Annexure margin once, and keep GST out of the variation.
1 / 3
Value the difference, not the whole
When the Superintendent directs a thicker slab over part of a floor, the slab depth in the bill is already measured and paid. The variation is the extra: the thickened area times the depth added. The same goes for reinforcement: only the bar schedule addendum, not the whole schedule again.
Primjer. Measuring the whole 260 mm depth would pay the first 200 mm twice.
Thickened area, 6.00 × 4.5027.00 m²
Depth added, 200 to 260 mm, m0.06
Extra concrete, m³1.62
2 / 3
Bill rate or agreed rate
AS 4000 values a variation in an order of preference: a price agreed beforehand, then the contract's own rates where they apply, then reasonable rates. A bill rate applies only where the work is of the same kind and done under the same conditions. Concrete and reinforcement in a thickening are the same work as in the slab. A 50 mm step in the soffit is not a full-height slab edge, so the edge formwork rate does not fit it, and a rate is agreed instead.
Primjer. Write down why each rate was chosen. The Superintendent will ask, and the answer is the line in the bill or the agreement.
3 / 3
Margin once, GST not at all
The Annexure may set a margin for off-site overheads and profit on a variation. It goes on once, on the total of the components. GST is not part of a variation's value: variations, like bill lines, are excluding GST. The tax is added once, at the foot of the payment claim.
Primjer. Margin 12 % of $2,100.00 is $252.00. The 12 % is that contract's Annexure choice, not a law.
1 Concrete at the bill rate
2 Reinforcement at the bill rate
3 Formwork and trimming, agreed rates
4 Margin, 12 %
5 Variation value
Price a slab thickening
Another job: a plant room floor thickened under a directed change.
Nije u mjerilu
Zadatak
Area thickened 6.4 m × 4.5 m, from 200 to 250 mm: 0.05 m added.
Bill rates: concrete $305.00 per m³, reinforcement $2,410.00 per t. Bar schedule addendum 360 kg.
Agreed rates: step formwork $35.20 per m round the thickened area; $76.00 for each of 4 new penetrations.
Annexure margin 12%.
Thickened area, m²28.8
Depth added, m0.05
Extra concrete, m³?
Thickened area, m²28.8
Depth added, m0.05
Extra concrete, m³1.44
Korak 1 od 4
Extra concrete
Thickened area times the depth added. How many m³?
Savjet: Only the extra depth, not the full slab.
6.4 m × 4.5 m × 0.05 m = 1.44 m³.
Korak 2 od 4
Components at bill rates
Concrete and reinforcement at the bill rates. What do the two come to?
Savjet: Reinforcement: kilograms to tonnes first.
Concrete 1.44 m³ × $305.00 = $439.20. Reinforcement 360 kg is 0.36 t × $2,410.00 = $867.60. Together $1,306.80.
$1,307$767
Bill rates $1,307
Step formwork $767
Penetrations $304
$1,307$767
Bill rates $1,307
Step formwork $767
Penetrations $304
Korak 3 od 4
Before the margin
Add the step formwork and the penetrations at the agreed rates. What is the variation before the margin?
Savjet: The step runs round the thickened area: its girth.
Girth 21.8 m × $35.20 = $767.36. Penetrations 4 × $76.00 = $304.00. With $1,306.80 that is $2,378.16.
1 Before the margin
2 Margin
3 Variation value
1 Before the margin
2 Margin
3 Variation value
Korak 4 od 4
Variation value
Add the Annexure margin. What is the value of the variation, excluding GST?
Savjet: Margin once, on the total. No GST.
$2,378.16 plus 12% is $2,663.54, excluding GST.
Ukratko. Measure the extra only. Bill rates where the work is the same, agreed rates where it is not. Margin once, GST later.
Provjerite se
Pitanje 1 od 3
A direction adds a 50 mm soffit step. The bill has edge formwork at 250 mm high. Which rate do you use?
The height is part of the description. A different height is different work.
Where no contract rate applies, a rate is agreed or a reasonable rate is used.
Formwork is a measured item in this bill.
Scaling is a way to reach an agreed rate, not the bill rate itself.
Pitanje 2 od 3
Where does GST go when you price a variation?
Variations are excluding GST, like the bill.
That still puts it in the variation.
The tax follows the claim, not each line.
Construction work is a taxable supply. The tax is added on the claim.
Pitanje 3 od 3
Components at bill and agreed rates total $5,240.00. The Annexure margin is 8 %. What is the variation value, excluding GST?