OpenConstruction Academy
התחברות / הרשמה
HE

תיאוריה לפני משימה 5 · 12 דק׳

Abnormal weather and a concurrent delay

מזג אוויר חריג ועיכוב מקביל

אחרי ההרצאה הזו תוכלו

  1. Say what A201-2017 asks of a claim for time based on adverse weather.
  2. Separate abnormal weather from the normal weather already planned, and measure its effect on the current update.
  3. Keep a concurrent delay of your own out of the extension.
1 / 4

Weather under A201-2017

Section 8.3.1 lists adverse weather conditions, documented in accordance with Section 15.1.6.2, among the causes for which the Contract Time is extended. Section 15.1.6.2 asks for data substantiating three things: the weather was abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction. In US practice weather is the textbook excusable, non-compensable delay: it can earn time, not money.

דוגמה. A rainy week in a rainy month proves nothing. The claim compares the days lost with the weather normals for those weeks, and shows the effect in the schedule.
2 / 4

Normal weather is already planned

The outdoor durations already hold the adverse days the weather normals predict for the season. Those days were priced and planned from the start. Only the days lost beyond them are abnormal. Claiming every lost day asks the owner to pay twice for the same rain.

דוגמה. Sitework planned with 4 normal adverse days loses 9 days to rain and frozen ground: 9 − 4 = 5 days are abnormal.
36
  • Dry working days 36
  • Normal adverse days, planned in 4
3 / 4

The effect on the scheduled construction

Abnormal days on a path with float use the float first, as a change does. Measure on the current update, with every earlier change in it. Earlier changes may have spent float on that path, or given float back by moving another path. The float of an old update gives the wrong answer either way.

דוגמה. 9 days lost, 4 normal, 3 days of float left: the finish moves by 2 working days.
91-42-3324
  • 1 Days lost
  • 2 Normal days already planned
  • 3 Float on the path, current update
  • 4 Delay to Substantial Completion
4 / 4

Concurrent delay

Sometimes your own subcontractor holds up the work in the same weeks as the weather. A201 has no clause on concurrent delay; common practice, and the stated practice in this course, is to measure the excusable event alone and give time for it, with no money for either party. Your own delay is not entered in the analysis and earns nothing.

דוגמה. The extension is 4 days, the weather's effect alone. The other 2 days of slip are yours to recover.
Weather alone, on the current update
4
Weather and your own delay together
6 (4 + 2)

Rain on the site utilities

Another job. Site utilities and paving lost days to rain in March, while your roofer missed days on a critical activity in the same weeks.

לא בקנה מידה
הבעיה
  • Daily reports: 11 working days lost on site utilities and paving.
  • Weather normals for those weeks: 4 adverse days, already in the duration.
  • Total float of that path on the current update: 5.
  • With the weather and the roofer both in, the finish would move 3 working days.
  • Substantial Completion: Monday, June 7, 2027.
שלב 1 מתוך 4

Abnormal days

How many of the lost days are abnormal?

11 − 4 = 7 abnormal days.

111-42-53?4
  • 1 Days lost
  • 2 Normal days
  • 3 Float
  • 4 Delay from the weather
111-42-5324
  • 1 Days lost
  • 2 Normal days
  • 3 Float
  • 4 Delay from the weather
שלב 2 מתוך 4

Effect on the finish

By how many working days does the weather alone move Substantial Completion?

7 − 5 = 2 working days reach the finish.

Weather alone
2
Weather and roofer
?
Weather alone
2
Weather and roofer
3 (2 + 1)
שלב 3 מתוך 4

Your own share

How many working days of the slip stay your own risk, with no time and no money?

3 − 2 = 1. The roofer's no-show is not entered in the analysis; recovering that day is your job.

שלב 4 מתוך 4

In calendar days

Substantial Completion was Monday, June 7, 2027. What extension in calendar days does the weather earn?

2 working days from Monday end on Wednesday, June 9. No weekend lies between, so the extension is 2 calendar days.

בקצרה. Lost days less normal days, less the float left on the current update. Measure the weather alone; your own delay earns nothing.

בדקו את עצמכם

שאלה 1 מתוך 3

Paving lost 9 working days to rain. The weather normals, already in its duration, give 2 adverse days. The path has 3 working days of float on the current update. By how many working days does the weather move Substantial Completion?

9 − 2 = 7 abnormal days. 7 − 3 = 4 working days reach the finish.
שאלה 2 מתוך 3

In the same weeks, abnormal weather and your own electrician both hold up the finish. What does the case practice give you?

  • Right. The excusable event earns time; neither delay earns money.

  • Your own delay earns nothing, and the two ran over the same weeks.

  • Your delay does not cancel an excusable one. Measured alone, the weather still earns its time.

שאלה 3 מתוך 3

Which evidence does A201-2017 Section 15.1.6.2 ask for in a weather claim?

  • Right. Daily reports, weather normals and the schedule analysis together cover all three.

  • Rain alone is expected. The claim has to show it was worse than normal and that it moved the schedule.

  • Lost days are the start. They must be set against the normals and shown to affect the scheduled work.