Say what A201-2017 asks of a claim for time based on adverse weather.
Separate abnormal weather from the normal weather already planned, and measure its effect on the current update.
Keep a concurrent delay of your own out of the extension.
1 / 4
Weather under A201-2017
Section 8.3.1 lists adverse weather conditions, documented in accordance with Section 15.1.6.2, among the causes for which the Contract Time is extended. Section 15.1.6.2 asks for data substantiating three things: the weather was abnormal for the period of time, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction. In US practice weather is the textbook excusable, non-compensable delay: it can earn time, not money.
ตัวอย่าง. A rainy week in a rainy month proves nothing. The claim compares the days lost with the weather normals for those weeks, and shows the effect in the schedule.
2 / 4
Normal weather is already planned
The outdoor durations already hold the adverse days the weather normals predict for the season. Those days were priced and planned from the start. Only the days lost beyond them are abnormal. Claiming every lost day asks the owner to pay twice for the same rain.
ตัวอย่าง. Sitework planned with 4 normal adverse days loses 9 days to rain and frozen ground: 9 − 4 = 5 days are abnormal.
36
Dry working days 36
Normal adverse days, planned in 4
3 / 4
The effect on the scheduled construction
Abnormal days on a path with float use the float first, as a change does. Measure on the current update, with every earlier change in it. Earlier changes may have spent float on that path, or given float back by moving another path. The float of an old update gives the wrong answer either way.
ตัวอย่าง. 9 days lost, 4 normal, 3 days of float left: the finish moves by 2 working days.
1 Days lost
2 Normal days already planned
3 Float on the path, current update
4 Delay to Substantial Completion
4 / 4
Concurrent delay
Sometimes your own subcontractor holds up the work in the same weeks as the weather. A201 has no clause on concurrent delay; common practice, and the stated practice in this course, is to measure the excusable event alone and give time for it, with no money for either party. Your own delay is not entered in the analysis and earns nothing.
ตัวอย่าง. The extension is 4 days, the weather's effect alone. The other 2 days of slip are yours to recover.
Weather alone, on the current update
4
Weather and your own delay together
6 (4 + 2)
Rain on the site utilities
Another job. Site utilities and paving lost days to rain in March, while your roofer missed days on a critical activity in the same weeks.
ไม่ได้วาดตามมาตราส่วน
โจทย์
Daily reports: 11 working days lost on site utilities and paving.
Weather normals for those weeks: 4 adverse days, already in the duration.
Total float of that path on the current update: 5.
With the weather and the roofer both in, the finish would move 3 working days.
Substantial Completion: Monday, June 7, 2027.
ขั้นตอนที่ 1 จาก 4
Abnormal days
How many of the lost days are abnormal?
คำใบ้: Lost days less the normal days already planned.
11 − 4 = 7 abnormal days.
1 Days lost
2 Normal days
3 Float
4 Delay from the weather
1 Days lost
2 Normal days
3 Float
4 Delay from the weather
ขั้นตอนที่ 2 จาก 4
Effect on the finish
By how many working days does the weather alone move Substantial Completion?
คำใบ้: The abnormal days meet the path's float first.
7 − 5 = 2 working days reach the finish.
Weather alone
2
Weather and roofer
?
Weather alone
2
Weather and roofer
3 (2 + 1)
ขั้นตอนที่ 3 จาก 4
Your own share
How many working days of the slip stay your own risk, with no time and no money?
คำใบ้: Total slip with both delays, less what the weather alone causes.
3 − 2 = 1. The roofer's no-show is not entered in the analysis; recovering that day is your job.
ขั้นตอนที่ 4 จาก 4
In calendar days
Substantial Completion was Monday, June 7, 2027. What extension in calendar days does the weather earn?
คำใบ้: Count forward on a calendar. Is there a weekend in between?
2 working days from Monday end on Wednesday, June 9. No weekend lies between, so the extension is 2 calendar days.
สรุปสั้น ๆ. Lost days less normal days, less the float left on the current update. Measure the weather alone; your own delay earns nothing.
ทดสอบตัวเอง
คำถามที่ 1 จาก 3
Paving lost 9 working days to rain. The weather normals, already in its duration, give 2 adverse days. The path has 3 working days of float on the current update. By how many working days does the weather move Substantial Completion?
9 − 2 = 7 abnormal days. 7 − 3 = 4 working days reach the finish.
คำถามที่ 2 จาก 3
In the same weeks, abnormal weather and your own electrician both hold up the finish. What does the case practice give you?
Right. The excusable event earns time; neither delay earns money.
Your own delay earns nothing, and the two ran over the same weeks.
Your delay does not cancel an excusable one. Measured alone, the weather still earns its time.
คำถามที่ 3 จาก 3
Which evidence does A201-2017 Section 15.1.6.2 ask for in a weather claim?
Right. Daily reports, weather normals and the schedule analysis together cover all three.
Rain alone is expected. The claim has to show it was worse than normal and that it moved the schedule.
Lost days are the start. They must be set against the normals and shown to affect the scheduled work.