תיאוריה לפני משימה 4 · 6 דק׳

Weather: when it gives time and when it gives nothing

גשמי ספטמבר: זמן, אך לא כסף

אחרי ההרצאה הזו תוכלו

  1. Tell expected weather from unavoidable weather.
  2. Use a contract weather table.
  3. Say why weather gives time but no money.
1 / 3

Expected weather is priced in

A bidder knows it rains in autumn. Weather that had to be expected when the tender was priced is the contractor's risk and gives no extension. Good tender documents state the expected days per month, so the line is a number, not an argument.

דוגמה. Table: 3 rain days in October. Five lost: 2 days beyond the table.
Expected
€3
Lost
€5 (€3 + €2)
2 / 3

Beyond the table: time, no money

Weather beyond what was to be expected is an event neither party could avert: it extends the time (§ 6 (2) no. 1 c). Nobody is responsible, so there is no damage to claim. In the register it is a neutral cause.

דוגמה. Two frost days beyond the table on a critical pour: 2 days more, and no claim for the idle crew.
טעות נפוצה

Claiming every wet day

Claiming all lost days, or adding cost for them, tells the client you have not read the contract. Claim the excess, neutral, and keep your client-caused claims clean of weather.

דוגמה. Five lost against three expected: claim 2, not 5.

Days beyond the table

Different numbers from your task.

לא בקנה מידה
הבעיה
  • 6 days lost to frost in January.
  • The contract expects 3 frost days in January.
שלב 1 מתוך 1

Extension

How many days extend the time?

6 − 3 = 3.

בקצרה. Excess weather days only, neutral cause, no money.

בדקו את עצמכם

שאלה 1 מתוך 3

Unavoidable excess weather gives…

  • Right.

  • Nobody is responsible.

  • It gives time.

שאלה 2 מתוך 3

Where does the expected number of weather days come from?

  • Right.

  • It must be agreed.

  • It is fixed in the tender.

שאלה 3 מתוך 3

7 days lost, 4 expected. Extension?

7 − 4 = 3.

מקורות

טקסטים רשמיים חינמיים. השיעור מציין מספרי סעיפים ומנסח את הכללים במילים שלו.