Weather: when it gives time and when it gives nothing

ستمبر کی بارش: وقت، مگر رقم نہیں

اس لیکچر کے بعد آپ کر سکیں گے

  1. Tell expected weather from unavoidable weather.
  2. Use a contract weather table.
  3. Say why weather gives time but no money.
1 / 3

Expected weather is priced in

A bidder knows it rains in autumn. Weather that had to be expected when the tender was priced is the contractor's risk and gives no extension. Good tender documents state the expected days per month, so the line is a number, not an argument.

مثال. Table: 3 rain days in October. Five lost: 2 days beyond the table.
Expected
€3
Lost
€5 (€3 + €2)
2 / 3

Beyond the table: time, no money

Weather beyond what was to be expected is an event neither party could avert: it extends the time (§ 6 (2) no. 1 c). Nobody is responsible, so there is no damage to claim. In the register it is a neutral cause.

مثال. Two frost days beyond the table on a critical pour: 2 days more, and no claim for the idle crew.
عام غلطی

Claiming every wet day

Claiming all lost days, or adding cost for them, tells the client you have not read the contract. Claim the excess, neutral, and keep your client-caused claims clean of weather.

مثال. Five lost against three expected: claim 2, not 5.

Days beyond the table

Different numbers from your task.

پیمانے کے مطابق نہیں
مسئلہ
  • 6 days lost to frost in January.
  • The contract expects 3 frost days in January.
مرحلہ 1 از 1

Extension

How many days extend the time?

6 − 3 = 3.

مختصراً. Excess weather days only, neutral cause, no money.

خود کو جانچیں

سوال 1 از 3

Unavoidable excess weather gives…

  • Right.

  • Nobody is responsible.

  • It gives time.

سوال 2 از 3

Where does the expected number of weather days come from?

  • Right.

  • It must be agreed.

  • It is fixed in the tender.

سوال 3 از 3

7 days lost, 4 expected. Extension?

7 − 4 = 3.

سرکاری ماخذ

مفت سرکاری متن۔ سبق شقوں کے نمبر دیتا ہے اور قواعد اپنے الفاظ میں بیان کرتا ہے۔