OpenConstruction Academy
سائن ان / رجسٹر کریں
UR

ٹاسک 3 سے پہلے نظریہ · 9 منٹ

What a standstill costs: § 6 (6) VOB/B

تعطل کی لاگت کیا تھی

اس لیکچر کے بعد آپ کر سکیں گے

  1. Separate damage from price.
  2. Apply the duty to keep work going.
  3. Price idle labour, idle equipment and the longer site.
1 / 3

Damage is extra cost

A claim under § 6 (6) puts the contractor where it would be without the hindrance. That is the cost that would not exist: workers paid to wait, equipment hired to stand, the site office open for longer. Lost profit is owed only for intent or gross negligence.

مثال. Two weeks of a crane standing at €150.00 a day is €1,500.00 of damage over ten working days.
+€9,0001+€1,5002+€4,0003€14,5004
  • 1 Idle labour
  • 2 Idle equipment
  • 3 Site open longer
  • 4 Damage
2 / 3

Keep work going

§ 6 (3) asks the contractor to do what can reasonably be expected to continue. Moving idle workers to other work is that duty, and their productive hours are not damage. A claim that ignores it is easy to cut down.

مثال. Four of eight joiners moved to another site after two days: from day three only four are idle.
عام غلطی

Pricing the claim like a variation

A variation is priced with overheads and profit because it is new work. A standstill claim is not new work. Adding risk and profit, or general overheads, to it turns a sound claim into one the client can reject line by line.

مثال. €30,000.00 of proven cost stays €30,000.00; it does not become €31,800.00 with 6 % on top.

Idle hours with mitigation

Different numbers from your task.

پیمانے کے مطابق نہیں
مسئلہ
  • All 8 workers idle for 2 days, 8 hours a day.
  • Then 4 move to other work for the remaining 6 days.
مرحلہ 1 از 1

Idle hours

How many idle hours are claimed?

2 × 8 × 8 + 6 × 4 × 8 = 320.

مختصراً. Idle hours only; productive hours elsewhere are not damage.

خود کو جانچیں

سوال 1 از 3

When is lost profit owed under § 6 (6)?

  • Right.

  • Only in those cases.

  • It is owed in those cases.

سوال 2 از 3

Workers moved to another task during the stop are…

  • Right.

  • No half rate.

  • They were working.

سوال 3 از 3

Idle labour €6,000, idle hire €800, site 10 extra days at €500. Damage?

6,000 + 800 + 5,000 = 11,800.

سرکاری ماخذ

مفت سرکاری متن۔ سبق شقوں کے نمبر دیتا ہے اور قواعد اپنے الفاظ میں بیان کرتا ہے۔