Damage is extra cost
A claim under § 6 (6) puts the contractor where it would be without the hindrance. That is the cost that would not exist: workers paid to wait, equipment hired to stand, the site office open for longer. Lost profit is owed only for intent or gross negligence.
- 1 Idle labour
- 2 Idle equipment
- 3 Site open longer
- 4 Damage