Hindrance claims: notice to penalty (Germany, VOB/B)
On an invented German job: the shell of a fire station under a VOB/B contract with a town.

Who this course is for

The project and people are invented for training. The rules and contract forms are real.
You will be able to
Skills checked
- Send the hindrance notice under VOB/B § 6 (1) in writing to the client, with the cost of a standstill day
- Claim the extension under VOB/B § 6 (4): the hindrance, the restart and the less favourable season, in working days
- Price standstill damage under VOB/B § 6 (6): idle labour, idle formwork and site overheads, without profit
- Separate weather the contract table expects from weather beyond it: time for the excess, no money
- Check a contract penalty under VOB/B § 11 against the extended completion date and the reservation at acceptance
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks. The free tasks give a progress badge, not the certificate.
The certificate is included in the price.

Files you work with
Created in your OpenConstructionERP workspace the moment you enrol.
- parties2 records
Prices
€39one paymentPrice when sales open
Task 1 is free. Pay only if you want to go on. Start task 1 free
- All 5 tasks and the professional certificate
- No subscription, nothing renews
- No VAT added: the price is the total
Cheaper in the bundle Germany: 4 courses for €119 instead of €176
Buy now · €39Course not as described? We fix it or refund you.
Need a discount? Write to info@datadrivenconstruction.io
How pricing worksWhat next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses

Your roleProject Architect
Cost calculation to DIN 276 (Germany)
You are the project architect for a new office building of a public utility association, at design stage (work stage 3).
Intermediate2.5 h of studyFigures checked 20DE
Task 1 free, then €59Professional certificate

Your roleEstimator
Complete a GAEB X83 bill of quantities (Germany)
You are the estimator at a facade contractor bidding for the external thermal insulation system of an office building.
Intermediate2 h of studyFigures checked 22DE
Task 1 free, then €39Professional certificate

Your roleSite manager and billing
Measurement, variations and final account (Germany, VOB/B)
You are the site manager at the façade firm that built the external thermal insulation system of an office building, and now you bill the work under VOB/B.
Intermediate2 h of studyFigures checked 20DE
Task 1 free, then €39Professional certificate