Hindrance claims: notice to penalty (Germany, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Start task 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Fictional project
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Work in the ERP
5 tasks, about 1 h 30 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Structural engineerOwes the drawings, for the client
    • Late drawingsTask 1
  • Formwork foremanReports the crew
    • Idle hoursTask 3
YouSite manager (Bauleiter), shell contractor

Goes from you

    • NoticeTask 1
    • EoT claimsTask 2
    • Damage claimTask 3
    • Penalty replyTask 5
    The townClient, building department

The project and the people are fictional. Portraits are generated.

Your route through the job

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Task 1 · 10 min

    Put the stop on record today

    You produce
    The hindrance notice
    Document
    Behinderungsanzeige
    In the ERP
    Variations
  2. Claim

    Task 2 · 20 min

    The drawings arrive: how many days?

    You produce
    The extension of time
    Document
    EoT claim
    In the ERP
    Variations
  3. Claim

    Task 3 · 25 min

    What the standstill cost

    You produce
    The standstill damage
    Document
    Variation request
    In the ERP
    Variations
  4. Claim

    Task 4 · 15 min

    September rain: time, but no money

    You produce
    The weather days
    Document
    EoT claim, neutral
    In the ERP
    Variations
  5. Answer

    Task 5 · 20 min

    The penalty letter

    You produce
    The penalty you accept
    Document
    Reply to the client
    In the ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Task 1NoticeIn writing, to the client, today.
RestartStop
Task 2DaysDuration, restart, season.
SiteIdle
Task 3MoneyProven extra cost, no profit.
ExcessExpected
Task 4WeatherOnly the excess, time only.
LateExtended
Task 5PenaltyOnly delay after the extended date.

Blue is what the task adds; grey is carried over from before.

In short. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.