You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Alusta ülesannet 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Väljamõeldud projekt
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Töö ERP-s
Ülesandeid 5, umbes 1 h 30 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • Structural engineerOwes the drawings, for the client
    • Late drawingsÜlesanne 1
  • Formwork foremanReports the crew
    • Idle hoursÜlesanne 3
SinaSite manager (Bauleiter), shell contractor

Läheb sinult

    • NoticeÜlesanne 1
    • EoT claimsÜlesanne 2
    • Damage claimÜlesanne 3
    • Penalty replyÜlesanne 5
    The townClient, building department

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Ülesanne 1 · 10 min

    Pane seisak täna kirja

    Sinu tulemus
    The hindrance notice
    Dokument
    Behinderungsanzeige
    ERP-s
    Variations
  2. Claim

    Ülesanne 2 · 20 min

    Joonised saabuvad: mitu päeva?

    Sinu tulemus
    The extension of time
    Dokument
    EoT claim
    ERP-s
    Variations
  3. Claim

    Ülesanne 3 · 25 min

    Mis seisak maksis

    Sinu tulemus
    The standstill damage
    Dokument
    Variation request
    ERP-s
    Variations
  4. Claim

    Ülesanne 4 · 15 min

    Septembri vihm: aega, aga mitte raha

    Sinu tulemus
    The weather days
    Dokument
    EoT claim, neutral
    ERP-s
    Variations
  5. Answer

    Ülesanne 5 · 20 min

    Leppetrahvi kiri

    Sinu tulemus
    The penalty you accept
    Dokument
    Reply to the client
    ERP-s
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Ülesanne 1NoticeIn writing, to the client, today.
RestartStop
Ülesanne 2DaysDuration, restart, season.
SiteIdle
Ülesanne 3MoneyProven extra cost, no profit.
ExcessExpected
Ülesanne 4WeatherOnly the excess, time only.
LateExtended
Ülesanne 5PenaltyOnly delay after the extended date.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.