Introducere în curs · 3 min
Pretenții pentru împiedicare: de la notificare la penalitate (Germania, VOB/B)
You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.
Proiect fictiv- Job
- Fire station shell, appliance hall and workshop wing, completion 20 November 2026
- Contract
- VOB/B agreed as a whole, unit prices, public client
- Method
- Notice, extension and claim in the ERP's Variations module
- Lucru în ERP
- 5 sarcini, circa 1 h 30 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- Structural engineerOwes the drawings, for the client
- Late drawingsSarcina 1
- Formwork foremanReports the crew
- Idle hoursSarcina 3
TuSite manager (Bauleiter), shell contractorPleacă de la tine
- NoticeSarcina 1
- EoT claimsSarcina 2
- Damage claimSarcina 3
- Penalty replySarcina 5
Proiectul și persoanele sunt fictive. Portretele sunt generate.
Traseul tău prin proiect
One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.
Record
Sarcina 1 · 10 min
Consemnați oprirea astăzi
- Produci
- The hindrance notice
- Document
- Behinderungsanzeige
- În ERP
- Variations
Claim
Sarcina 2 · 20 min
Sosesc planurile: câte zile?
- Produci
- The extension of time
- Document
- EoT claim
- În ERP
- Variations
Claim
Sarcina 3 · 25 min
Ce a costat oprirea
- Produci
- The standstill damage
- Document
- Variation request
- În ERP
- Variations
Claim
Sarcina 4 · 15 min
Ploaia din septembrie: timp, dar fără bani
- Produci
- The weather days
- Document
- EoT claim, neutral
- În ERP
- Variations
Answer
Sarcina 5 · 20 min
Scrisoarea de penalitate
- Produci
- The penalty you accept
- Document
- Reply to the client
- În ERP
- Variations
How one late delivery becomes days, euros and a penalty
Each step below is one task.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.