Pretenții pentru împiedicare: de la notificare la penalitate (Germania, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Începe sarcina 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Proiect fictiv
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Lucru în ERP
5 sarcini, circa 1 h 30 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Structural engineerOwes the drawings, for the client
    • Late drawingsSarcina 1
  • Formwork foremanReports the crew
    • Idle hoursSarcina 3
TuSite manager (Bauleiter), shell contractor

Pleacă de la tine

    • NoticeSarcina 1
    • EoT claimsSarcina 2
    • Damage claimSarcina 3
    • Penalty replySarcina 5
    The townClient, building department

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Sarcina 1 · 10 min

    Consemnați oprirea astăzi

    Produci
    The hindrance notice
    Document
    Behinderungsanzeige
    În ERP
    Variations
  2. Claim

    Sarcina 2 · 20 min

    Sosesc planurile: câte zile?

    Produci
    The extension of time
    Document
    EoT claim
    În ERP
    Variations
  3. Claim

    Sarcina 3 · 25 min

    Ce a costat oprirea

    Produci
    The standstill damage
    Document
    Variation request
    În ERP
    Variations
  4. Claim

    Sarcina 4 · 15 min

    Ploaia din septembrie: timp, dar fără bani

    Produci
    The weather days
    Document
    EoT claim, neutral
    În ERP
    Variations
  5. Answer

    Sarcina 5 · 20 min

    Scrisoarea de penalitate

    Produci
    The penalty you accept
    Document
    Reply to the client
    În ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Sarcina 1NoticeIn writing, to the client, today.
RestartStop
Sarcina 2DaysDuration, restart, season.
SiteIdle
Sarcina 3MoneyProven extra cost, no profit.
ExcessExpected
Sarcina 4WeatherOnly the excess, time only.
LateExtended
Sarcina 5PenaltyOnly delay after the extended date.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.