You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Start oppgave 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Fiktivt prosjekt
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Arbeid i ERP
5 oppgaver, omtrent 1 t 30 min

Hvem gir hva til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til deg

  • Structural engineerOwes the drawings, for the client
    • Late drawingsOppgave 1
  • Formwork foremanReports the crew
    • Idle hoursOppgave 3
DuSite manager (Bauleiter), shell contractor

Går fra deg

    • NoticeOppgave 1
    • EoT claimsOppgave 2
    • Damage claimOppgave 3
    • Penalty replyOppgave 5
    The townClient, building department

Prosjektet og personene er fiktive. Portrettene er genererte.

Din vei gjennom prosjektet

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Oppgave 1 · 10 min

    Få stansen protokollført i dag

    Du leverer
    The hindrance notice
    Dokument
    Behinderungsanzeige
    I ERP
    Variations
  2. Claim

    Oppgave 2 · 20 min

    Tegningene kommer: hvor mange dager?

    Du leverer
    The extension of time
    Dokument
    EoT claim
    I ERP
    Variations
  3. Claim

    Oppgave 3 · 25 min

    Hva stansen kostet

    Du leverer
    The standstill damage
    Dokument
    Variation request
    I ERP
    Variations
  4. Claim

    Oppgave 4 · 15 min

    Septemberregn: tid, men ingen penger

    Du leverer
    The weather days
    Dokument
    EoT claim, neutral
    I ERP
    Variations
  5. Answer

    Oppgave 5 · 20 min

    Brevet om dagmulkt

    Du leverer
    The penalty you accept
    Dokument
    Reply to the client
    I ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Oppgave 1NoticeIn writing, to the client, today.
RestartStop
Oppgave 2DaysDuration, restart, season.
SiteIdle
Oppgave 3MoneyProven extra cost, no profit.
ExcessExpected
Oppgave 4WeatherOnly the excess, time only.
LateExtended
Oppgave 5PenaltyOnly delay after the extended date.

Blått er det oppgaven legger til; grått er overført fra før.

Kort sagt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.