Zahtjevi zbog ometanja: od obavijesti do ugovorne kazne (Njemačka, VOB/B)
You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.
Izmišljeni projekt- Job
- Fire station shell, appliance hall and workshop wing, completion 20 November 2026
- Contract
- VOB/B agreed as a whole, unit prices, public client
- Method
- Notice, extension and claim in the ERP's Variations module
- Rad u ERP-u
- Zadataka: 5, oko 1 h 30 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Structural engineerOwes the drawings, for the client
- Late drawingsZadatak 1
- Formwork foremanReports the crew
- Idle hoursZadatak 3
ViSite manager (Bauleiter), shell contractorOdlazi od vas
- NoticeZadatak 1
- EoT claimsZadatak 2
- Damage claimZadatak 3
- Penalty replyZadatak 5
Projekt i osobe su izmišljeni. Portreti su generirani.
Vaš put kroz projekt
One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.
Record
Zadatak 1 · 10 min
Zabilježite zastoj još danas
- Vaš rezultat
- The hindrance notice
- Dokument
- Behinderungsanzeige
- U ERP-u
- Variations
Claim
Zadatak 2 · 20 min
Nacrti stižu: koliko dana?
- Vaš rezultat
- The extension of time
- Dokument
- EoT claim
- U ERP-u
- Variations
Claim
Zadatak 3 · 25 min
Što je zastoj koštao
- Vaš rezultat
- The standstill damage
- Dokument
- Variation request
- U ERP-u
- Variations
Claim
Zadatak 4 · 15 min
Rujanska kiša: vrijeme, ali ne i novac
- Vaš rezultat
- The weather days
- Dokument
- EoT claim, neutral
- U ERP-u
- Variations
Answer
Zadatak 5 · 20 min
Pismo o kazni
- Vaš rezultat
- The penalty you accept
- Dokument
- Reply to the client
- U ERP-u
- Variations
How one late delivery becomes days, euros and a penalty
Each step below is one task.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.