OpenConstruction Academy
Prijava / Registracija
HR

Uvod u tečaj · 3 min

Zahtjevi zbog ometanja: od obavijesti do ugovorne kazne (Njemačka, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Započni zadatak 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Izmišljeni projekt
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Rad u ERP-u
Zadataka: 5, oko 1 h 30 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Structural engineerOwes the drawings, for the client
    • Late drawingsZadatak 1
  • Formwork foremanReports the crew
    • Idle hoursZadatak 3
ViSite manager (Bauleiter), shell contractor

Odlazi od vas

    • NoticeZadatak 1
    • EoT claimsZadatak 2
    • Damage claimZadatak 3
    • Penalty replyZadatak 5
    The townClient, building department

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Zadatak 1 · 10 min

    Zabilježite zastoj još danas

    Vaš rezultat
    The hindrance notice
    Dokument
    Behinderungsanzeige
    U ERP-u
    Variations
  2. Claim

    Zadatak 2 · 20 min

    Nacrti stižu: koliko dana?

    Vaš rezultat
    The extension of time
    Dokument
    EoT claim
    U ERP-u
    Variations
  3. Claim

    Zadatak 3 · 25 min

    Što je zastoj koštao

    Vaš rezultat
    The standstill damage
    Dokument
    Variation request
    U ERP-u
    Variations
  4. Claim

    Zadatak 4 · 15 min

    Rujanska kiša: vrijeme, ali ne i novac

    Vaš rezultat
    The weather days
    Dokument
    EoT claim, neutral
    U ERP-u
    Variations
  5. Answer

    Zadatak 5 · 20 min

    Pismo o kazni

    Vaš rezultat
    The penalty you accept
    Dokument
    Reply to the client
    U ERP-u
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Zadatak 1NoticeIn writing, to the client, today.
RestartStop
Zadatak 2DaysDuration, restart, season.
SiteIdle
Zadatak 3MoneyProven extra cost, no profit.
ExcessExpected
Zadatak 4WeatherOnly the excess, time only.
LateExtended
Zadatak 5PenaltyOnly delay after the extended date.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.