Introduktion til kurset · 3 min

Hindringskrav: fra varsel til dagbod (Tyskland, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Start opgave 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Fiktivt projekt
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Arbejde i ERP
5 opgaver, cirka 1 t 30 min

Hvem giver hvad til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • Structural engineerOwes the drawings, for the client
    • Late drawingsOpgave 1
  • Formwork foremanReports the crew
    • Idle hoursOpgave 3
DigSite manager (Bauleiter), shell contractor

Går fra dig

    • NoticeOpgave 1
    • EoT claimsOpgave 2
    • Damage claimOpgave 3
    • Penalty replyOpgave 5
    The townClient, building department

Projektet og personerne er fiktive. Portrætterne er genererede.

Din vej gennem sagen

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Opgave 1 · 10 min

    Få stilstanden på papiret i dag

    Du leverer
    The hindrance notice
    Dokument
    Behinderungsanzeige
    I ERP
    Variations
  2. Claim

    Opgave 2 · 20 min

    Tegningerne kommer: hvor mange dage?

    Du leverer
    The extension of time
    Dokument
    EoT claim
    I ERP
    Variations
  3. Claim

    Opgave 3 · 25 min

    Hvad stilstanden kostede

    Du leverer
    The standstill damage
    Dokument
    Variation request
    I ERP
    Variations
  4. Claim

    Opgave 4 · 15 min

    Septemberregn: tid, men ingen penge

    Du leverer
    The weather days
    Dokument
    EoT claim, neutral
    I ERP
    Variations
  5. Answer

    Opgave 5 · 20 min

    Bodsbrevet

    Du leverer
    The penalty you accept
    Dokument
    Reply to the client
    I ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Opgave 1NoticeIn writing, to the client, today.
RestartStop
Opgave 2DaysDuration, restart, season.
SiteIdle
Opgave 3MoneyProven extra cost, no profit.
ExcessExpected
Opgave 4WeatherOnly the excess, time only.
LateExtended
Opgave 5PenaltyOnly delay after the extended date.

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.