Inleiding tot de cursus · 3 min

Claims bij hindernis: van melding tot boete (Duitsland, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Start opdracht 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Fictief project
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Werk in de ERP
5 opdrachten, ongeveer 1 u 30 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Structural engineerOwes the drawings, for the client
    • Late drawingsOpdracht 1
  • Formwork foremanReports the crew
    • Idle hoursOpdracht 3
USite manager (Bauleiter), shell contractor

Gaat van u uit

    • NoticeOpdracht 1
    • EoT claimsOpdracht 2
    • Damage claimOpdracht 3
    • Penalty replyOpdracht 5
    The townClient, building department

Het project en de mensen zijn fictief. De portretten zijn gegenereerd.

Uw route door het project

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Opdracht 1 · 10 min

    Leg de stilstand vandaag vast

    U levert
    The hindrance notice
    Document
    Behinderungsanzeige
    In de ERP
    Variations
  2. Claim

    Opdracht 2 · 20 min

    De tekeningen komen binnen: hoeveel dagen?

    U levert
    The extension of time
    Document
    EoT claim
    In de ERP
    Variations
  3. Claim

    Opdracht 3 · 25 min

    Wat de stilstand kostte

    U levert
    The standstill damage
    Document
    Variation request
    In de ERP
    Variations
  4. Claim

    Opdracht 4 · 15 min

    Regen in september: tijd, maar geen geld

    U levert
    The weather days
    Document
    EoT claim, neutral
    In de ERP
    Variations
  5. Answer

    Opdracht 5 · 20 min

    De boetebrief

    U levert
    The penalty you accept
    Document
    Reply to the client
    In de ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Opdracht 1NoticeIn writing, to the client, today.
RestartStop
Opdracht 2DaysDuration, restart, season.
SiteIdle
Opdracht 3MoneyProven extra cost, no profit.
ExcessExpected
Opdracht 4WeatherOnly the excess, time only.
LateExtended
Opdracht 5PenaltyOnly delay after the extended date.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.