Въведение в курса · 3 мин

Искове за възпрепятстване: от уведомлението до неустойката (Германия, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Започнете задача 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Измислен проект
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Работа в ERP
Задачи: 5, около 1 ч 30 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Structural engineerOwes the drawings, for the client
    • Late drawingsЗадача 1
  • Formwork foremanReports the crew
    • Idle hoursЗадача 3
ВиеSite manager (Bauleiter), shell contractor

Тръгва от вас

    • NoticeЗадача 1
    • EoT claimsЗадача 2
    • Damage claimЗадача 3
    • Penalty replyЗадача 5
    The townClient, building department

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Задача 1 · 10 мин

    Запишете спирането още днес

    Вашият резултат
    The hindrance notice
    Документ
    Behinderungsanzeige
    В ERP
    Variations
  2. Claim

    Задача 2 · 20 мин

    Чертежите пристигат: колко дни?

    Вашият резултат
    The extension of time
    Документ
    EoT claim
    В ERP
    Variations
  3. Claim

    Задача 3 · 25 мин

    Колко струва престоят

    Вашият резултат
    The standstill damage
    Документ
    Variation request
    В ERP
    Variations
  4. Claim

    Задача 4 · 15 мин

    Септемврийски дъжд: време, но не пари

    Вашият резултат
    The weather days
    Документ
    EoT claim, neutral
    В ERP
    Variations
  5. Answer

    Задача 5 · 20 мин

    Писмото за неустойка

    Вашият резултат
    The penalty you accept
    Документ
    Reply to the client
    В ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Задача 1NoticeIn writing, to the client, today.
RestartStop
Задача 2DaysDuration, restart, season.
SiteIdle
Задача 3MoneyProven extra cost, no profit.
ExcessExpected
Задача 4WeatherOnly the excess, time only.
LateExtended
Задача 5PenaltyOnly delay after the extended date.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.