Mga claim sa hadlang: mula abiso hanggang multa (Germany, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Simulan ang gawain 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Kathang-isip na proyekto
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Trabaho sa ERP
5 gawain, mga 1 oras 30 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Structural engineerOwes the drawings, for the client
    • Late drawingsGawain 1
  • Formwork foremanReports the crew
    • Idle hoursGawain 3
IkawSite manager (Bauleiter), shell contractor

Lumalabas sa iyo

    • NoticeGawain 1
    • EoT claimsGawain 2
    • Damage claimGawain 3
    • Penalty replyGawain 5
    The townClient, building department

Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.

Ang ruta mo sa proyekto

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Gawain 1 · 10 min

    Itala ang pagtigil ngayon din

    Ang gagawin mo
    The hindrance notice
    Dokumento
    Behinderungsanzeige
    Sa ERP
    Variations
  2. Claim

    Gawain 2 · 20 min

    Dumating ang mga drowing: ilang araw?

    Ang gagawin mo
    The extension of time
    Dokumento
    EoT claim
    Sa ERP
    Variations
  3. Claim

    Gawain 3 · 25 min

    Ang inabot ng pagtigil

    Ang gagawin mo
    The standstill damage
    Dokumento
    Variation request
    Sa ERP
    Variations
  4. Claim

    Gawain 4 · 15 min

    Ulan noong Setyembre: oras, ngunit walang pera

    Ang gagawin mo
    The weather days
    Dokumento
    EoT claim, neutral
    Sa ERP
    Variations
  5. Answer

    Gawain 5 · 20 min

    Ang liham ng multa

    Ang gagawin mo
    The penalty you accept
    Dokumento
    Reply to the client
    Sa ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Gawain 1NoticeIn writing, to the client, today.
RestartStop
Gawain 2DaysDuration, restart, season.
SiteIdle
Gawain 3MoneyProven extra cost, no profit.
ExcessExpected
Gawain 4WeatherOnly the excess, time only.
LateExtended
Gawain 5PenaltyOnly delay after the extended date.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.