Panimula ng kurso · 3 min
Mga claim sa hadlang: mula abiso hanggang multa (Germany, VOB/B)
You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.
Kathang-isip na proyekto- Job
- Fire station shell, appliance hall and workshop wing, completion 20 November 2026
- Contract
- VOB/B agreed as a whole, unit prices, public client
- Method
- Notice, extension and claim in the ERP's Variations module
- Trabaho sa ERP
- 5 gawain, mga 1 oras 30 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Structural engineerOwes the drawings, for the client
- Late drawingsGawain 1
- Formwork foremanReports the crew
- Idle hoursGawain 3
IkawSite manager (Bauleiter), shell contractorLumalabas sa iyo
- NoticeGawain 1
- EoT claimsGawain 2
- Damage claimGawain 3
- Penalty replyGawain 5
Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.
Ang ruta mo sa proyekto
One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.
Record
Gawain 1 · 10 min
Itala ang pagtigil ngayon din
- Ang gagawin mo
- The hindrance notice
- Dokumento
- Behinderungsanzeige
- Sa ERP
- Variations
Claim
Gawain 2 · 20 min
Dumating ang mga drowing: ilang araw?
- Ang gagawin mo
- The extension of time
- Dokumento
- EoT claim
- Sa ERP
- Variations
Claim
Gawain 3 · 25 min
Ang inabot ng pagtigil
- Ang gagawin mo
- The standstill damage
- Dokumento
- Variation request
- Sa ERP
- Variations
Claim
Gawain 4 · 15 min
Ulan noong Setyembre: oras, ngunit walang pera
- Ang gagawin mo
- The weather days
- Dokumento
- EoT claim, neutral
- Sa ERP
- Variations
Answer
Gawain 5 · 20 min
Ang liham ng multa
- Ang gagawin mo
- The penalty you accept
- Dokumento
- Reply to the client
- Sa ERP
- Variations
How one late delivery becomes days, euros and a penalty
Each step below is one task.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.