Hinderanspråk: från anmälan till vite (Tyskland, VOB/B)
You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.
Fiktivt projekt- Job
- Fire station shell, appliance hall and workshop wing, completion 20 November 2026
- Contract
- VOB/B agreed as a whole, unit prices, public client
- Method
- Notice, extension and claim in the ERP's Variations module
- Arbete i ERP
- 5 uppgifter, cirka 1 h 30 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Structural engineerOwes the drawings, for the client
- Late drawingsUppgift 1
- Formwork foremanReports the crew
- Idle hoursUppgift 3
DuSite manager (Bauleiter), shell contractorGår från dig
- NoticeUppgift 1
- EoT claimsUppgift 2
- Damage claimUppgift 3
- Penalty replyUppgift 5
Projektet och personerna är fiktiva. Porträtten är genererade.
Din väg genom projektet
One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.
Record
Uppgift 1 · 10 min
Dokumentera stilleståndet i dag
- Du tar fram
- The hindrance notice
- Dokument
- Behinderungsanzeige
- I ERP
- Variations
Claim
Uppgift 2 · 20 min
Ritningarna kommer: hur många dagar?
- Du tar fram
- The extension of time
- Dokument
- EoT claim
- I ERP
- Variations
Claim
Uppgift 3 · 25 min
Vad stilleståndet kostade
- Du tar fram
- The standstill damage
- Dokument
- Variation request
- I ERP
- Variations
Claim
Uppgift 4 · 15 min
Septemberregn: tid, men inga pengar
- Du tar fram
- The weather days
- Dokument
- EoT claim, neutral
- I ERP
- Variations
Answer
Uppgift 5 · 20 min
Vitesbrevet
- Du tar fram
- The penalty you accept
- Dokument
- Reply to the client
- I ERP
- Variations
How one late delivery becomes days, euros and a penalty
Each step below is one task.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.