OpenConstruction Academy
Logga in / Registrera
SV

Introduktion till kursen · 3 min

Hinderanspråk: från anmälan till vite (Tyskland, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

Starta uppgift 1

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Fiktivt projekt
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
Arbete i ERP
5 uppgifter, cirka 1 h 30 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Structural engineerOwes the drawings, for the client
    • Late drawingsUppgift 1
  • Formwork foremanReports the crew
    • Idle hoursUppgift 3
DuSite manager (Bauleiter), shell contractor

Går från dig

    • NoticeUppgift 1
    • EoT claimsUppgift 2
    • Damage claimUppgift 3
    • Penalty replyUppgift 5
    The townClient, building department

Projektet och personerna är fiktiva. Porträtten är genererade.

Din väg genom projektet

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    Uppgift 1 · 10 min

    Dokumentera stilleståndet i dag

    Du tar fram
    The hindrance notice
    Dokument
    Behinderungsanzeige
    I ERP
    Variations
  2. Claim

    Uppgift 2 · 20 min

    Ritningarna kommer: hur många dagar?

    Du tar fram
    The extension of time
    Dokument
    EoT claim
    I ERP
    Variations
  3. Claim

    Uppgift 3 · 25 min

    Vad stilleståndet kostade

    Du tar fram
    The standstill damage
    Dokument
    Variation request
    I ERP
    Variations
  4. Claim

    Uppgift 4 · 15 min

    Septemberregn: tid, men inga pengar

    Du tar fram
    The weather days
    Dokument
    EoT claim, neutral
    I ERP
    Variations
  5. Answer

    Uppgift 5 · 20 min

    Vitesbrevet

    Du tar fram
    The penalty you accept
    Dokument
    Reply to the client
    I ERP
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
Uppgift 1NoticeIn writing, to the client, today.
RestartStop
Uppgift 2DaysDuration, restart, season.
SiteIdle
Uppgift 3MoneyProven extra cost, no profit.
ExcessExpected
Uppgift 4WeatherOnly the excess, time only.
LateExtended
Uppgift 5PenaltyOnly delay after the extended date.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.