Тоскоолдук талаптары: билдирүүдөн айыпка чейин (Германия, VOB/B)

You are the site manager of the shell contractor on a fire station for a German town, under VOB/B. The reinforcement drawings for the appliance-hall slab are late and your formwork crew stands. In five tasks you take the stop from the first notice to the penalty letter: the notice, the days, the money, the weather and the deduction.

1-тапшырманы баштоо

A fire station shell under construction: the walls of the appliance hall stand, the slab formwork is not yet set.Ойдон чыгарылган долбоор
Feuerwache Sellenried, RohbauOctober 2026: the slab waits
Job
Fire station shell, appliance hall and workshop wing, completion 20 November 2026
Contract
VOB/B agreed as a whole, unit prices, public client
Method
Notice, extension and claim in the ERP's Variations module
ERPдеги иш
Тапшырмалар: 5, болжол менен 1 саат 30 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Structural engineerOwes the drawings, for the client
    • Late drawings1-тапшырма
  • Formwork foremanReports the crew
    • Idle hours3-тапшырма
СизSite manager (Bauleiter), shell contractor

Сизден кетет

    • Notice1-тапшырма
    • EoT claims2-тапшырма
    • Damage claim3-тапшырма
    • Penalty reply5-тапшырма
    The townClient, building department

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

One hindrance, handled in the order a site manager handles it. Task 1 is free: in Variations you send the notice.

  1. Record

    1-тапшырма · 10 мүн

    Токтоп турууну бүгүн каттаңыз

    Натыйжа
    The hindrance notice
    Документ
    Behinderungsanzeige
    ERPде
    Variations
  2. Claim

    2-тапшырма · 20 мүн

    Чиймелер келди: канча күн?

    Натыйжа
    The extension of time
    Документ
    EoT claim
    ERPде
    Variations
  3. Claim

    3-тапшырма · 25 мүн

    Токтоп туруу канча турду

    Натыйжа
    The standstill damage
    Документ
    Variation request
    ERPде
    Variations
  4. Claim

    4-тапшырма · 15 мүн

    Сентябрдагы жамгыр: убакыт, бирок акча эмес

    Натыйжа
    The weather days
    Документ
    EoT claim, neutral
    ERPде
    Variations
  5. Answer

    5-тапшырма · 20 мүн

    Айып пул каты

    Натыйжа
    The penalty you accept
    Документ
    Reply to the client
    ERPде
    Variations

How one late delivery becomes days, euros and a penalty

Each step below is one task.

Notice
1-тапшырмаNoticeIn writing, to the client, today.
RestartStop
2-тапшырмаDaysDuration, restart, season.
SiteIdle
3-тапшырмаMoneyProven extra cost, no profit.
ExcessExpected
4-тапшырмаWeatherOnly the excess, time only.
LateExtended
5-тапшырмаPenaltyOnly delay after the extended date.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Put it in writing, count the contract's days, claim cost not profit, keep weather apart, and pay a penalty only for real delay.