Cheat sheet
Hindrance claims: notice to penalty (Germany, VOB/B)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- In writing, to the client, today. A word on site or a diary line is not a hindrance notice.
- How it is built
- Cost of a standstill day = Crew × hours × wage + Formwork hire
- Usual mistake
- That is the crew alone. The hired slab formwork stands too and costs every working day.
- At work
- The site manager writes the notice the first morning and sends it to the client, copying the architect.
- Rule
- Duration, restart, season. § 6 (4) has three parts, counted in the contract's working days.
- How it is built
- Extension for the drawings = Stop + Restart + Season
- Usual mistake
- That is the stop alone. § 6 (4) adds a surcharge for the restart and for the shift into December.
- At work
- The claim lists each part of § 6 (4) with its reason, in the contract's working days.
- Rule
- Damage is cost, not price. Idle hours, idle hire, the longer site; no profit, and no hours that were working elsewhere.
- How it is built
- Idle labour hours = Days 1-3: 6 × 8 + Days 4-12: 3 × 8
- Usual mistake
- All six carpenters for twelve days. Three were productive from day 4.
- At work
- The site manager builds the claim from the foreman's daily crew lists and the hire invoices.
- Rule
- Expected weather is your risk. Only days beyond the contract's table extend the time, and they bring no money.
- How it is built
- Total extension = Drawings claim + Rain beyond the table
- Usual mistake
- The total includes all four rain days. Only the two beyond the weather table extend the time.
- At work
- Each delay event gets its own claim with its own cause, so the client can accept one without the other.
- Rule
- No delay, no penalty. Count from the extended date, in the contract's days; the cap is a ceiling.
- How it is built
- Penalty owed = Working days after the extended date × 0.2 % of the net contract sum
- Usual mistake
- That is the client's figure, counted from the original date. Both extensions move the completion date first.
- At work
- The commercial reply accepts what is owed, rejects the rest in writing and keeps the file for the final account.