Hindrance claims: notice to penalty (Germany, VOB/B)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Put the stop on record today

Theory (7 min)
Rule
In writing, to the client, today. A word on site or a diary line is not a hindrance notice.
How it is built
  • Cost of a standstill day = Crew × hours × wage + Formwork hire
Usual mistake
That is the crew alone. The hired slab formwork stands too and costs every working day.
At work
The site manager writes the notice the first morning and sends it to the client, copying the architect.

Task 2

The drawings arrive: how many days?

Theory (8 min)
Rule
Duration, restart, season. § 6 (4) has three parts, counted in the contract's working days.
How it is built
  • Extension for the drawings = Stop + Restart + Season
Usual mistake
That is the stop alone. § 6 (4) adds a surcharge for the restart and for the shift into December.
At work
The claim lists each part of § 6 (4) with its reason, in the contract's working days.

Task 3

What the standstill cost

Theory (9 min)
Rule
Damage is cost, not price. Idle hours, idle hire, the longer site; no profit, and no hours that were working elsewhere.
How it is built
  • Idle labour hours = Days 1-3: 6 × 8 + Days 4-12: 3 × 8
Usual mistake
All six carpenters for twelve days. Three were productive from day 4.
At work
The site manager builds the claim from the foreman's daily crew lists and the hire invoices.

Task 4

September rain: time, but no money

Theory (6 min)
Rule
Expected weather is your risk. Only days beyond the contract's table extend the time, and they bring no money.
How it is built
  • Total extension = Drawings claim + Rain beyond the table
Usual mistake
The total includes all four rain days. Only the two beyond the weather table extend the time.
At work
Each delay event gets its own claim with its own cause, so the client can accept one without the other.

Task 5

The penalty letter

Theory (7 min)
Rule
No delay, no penalty. Count from the extended date, in the contract's days; the cap is a ceiling.
How it is built
  • Penalty owed = Working days after the extended date × 0.2 % of the net contract sum
Usual mistake
That is the client's figure, counted from the original date. Both extensions move the completion date first.
At work
The commercial reply accepts what is owed, rejects the rest in writing and keeps the file for the final account.