3-тапшырма алдындагы теория · 9 мүн

What a standstill costs: § 6 (6) VOB/B

Токтоп туруу канча турду

Бул лекциядан кийин сиз төмөнкүнү үйрөнөсүз

  1. Separate damage from price.
  2. Apply the duty to keep work going.
  3. Price idle labour, idle equipment and the longer site.
1 / 3

Damage is extra cost

A claim under § 6 (6) puts the contractor where it would be without the hindrance. That is the cost that would not exist: workers paid to wait, equipment hired to stand, the site office open for longer. Lost profit is owed only for intent or gross negligence.

Мисал. Two weeks of a crane standing at €150.00 a day is €1,500.00 of damage over ten working days.
+€9,0001+€1,5002+€4,0003€14,5004
  • 1 Idle labour
  • 2 Idle equipment
  • 3 Site open longer
  • 4 Damage
2 / 3

Keep work going

§ 6 (3) asks the contractor to do what can reasonably be expected to continue. Moving idle workers to other work is that duty, and their productive hours are not damage. A claim that ignores it is easy to cut down.

Мисал. Four of eight joiners moved to another site after two days: from day three only four are idle.
Көп кездешкен ката

Pricing the claim like a variation

A variation is priced with overheads and profit because it is new work. A standstill claim is not new work. Adding risk and profit, or general overheads, to it turns a sound claim into one the client can reject line by line.

Мисал. €30,000.00 of proven cost stays €30,000.00; it does not become €31,800.00 with 6 % on top.

Idle hours with mitigation

Different numbers from your task.

Масштабсыз
Маселе
  • All 8 workers idle for 2 days, 8 hours a day.
  • Then 4 move to other work for the remaining 6 days.
1 кадамдын 1-си

Idle hours

How many idle hours are claimed?

2 × 8 × 8 + 6 × 4 × 8 = 320.

Кыскача. Idle hours only; productive hours elsewhere are not damage.

Өзүңүздү текшериңиз

3 суроонун 1-си

When is lost profit owed under § 6 (6)?

  • Right.

  • Only in those cases.

  • It is owed in those cases.

3 суроонун 2-си

Workers moved to another task during the stop are…

  • Right.

  • No half rate.

  • They were working.

3 суроонун 3-си

Idle labour €6,000, idle hire €800, site 10 extra days at €500. Damage?

6,000 + 800 + 5,000 = 11,800.