OpenConstruction Academy
เข้าสู่ระบบ / สมัครสมาชิก
TH

ทฤษฎีก่อนงานที่ 3 · 9 นาที

What a standstill costs: § 6 (6) VOB/B

การหยุดงานเสียค่าใช้จ่ายเท่าใด

หลังจบบทเรียนนี้ คุณจะสามารถ

  1. Separate damage from price.
  2. Apply the duty to keep work going.
  3. Price idle labour, idle equipment and the longer site.
1 / 3

Damage is extra cost

A claim under § 6 (6) puts the contractor where it would be without the hindrance. That is the cost that would not exist: workers paid to wait, equipment hired to stand, the site office open for longer. Lost profit is owed only for intent or gross negligence.

ตัวอย่าง. Two weeks of a crane standing at €150.00 a day is €1,500.00 of damage over ten working days.
+€9,0001+€1,5002+€4,0003€14,5004
  • 1 Idle labour
  • 2 Idle equipment
  • 3 Site open longer
  • 4 Damage
2 / 3

Keep work going

§ 6 (3) asks the contractor to do what can reasonably be expected to continue. Moving idle workers to other work is that duty, and their productive hours are not damage. A claim that ignores it is easy to cut down.

ตัวอย่าง. Four of eight joiners moved to another site after two days: from day three only four are idle.
ข้อผิดพลาดที่พบบ่อย

Pricing the claim like a variation

A variation is priced with overheads and profit because it is new work. A standstill claim is not new work. Adding risk and profit, or general overheads, to it turns a sound claim into one the client can reject line by line.

ตัวอย่าง. €30,000.00 of proven cost stays €30,000.00; it does not become €31,800.00 with 6 % on top.

Idle hours with mitigation

Different numbers from your task.

ไม่ได้วาดตามมาตราส่วน
โจทย์
  • All 8 workers idle for 2 days, 8 hours a day.
  • Then 4 move to other work for the remaining 6 days.
ขั้นตอนที่ 1 จาก 1

Idle hours

How many idle hours are claimed?

2 × 8 × 8 + 6 × 4 × 8 = 320.

สรุปสั้น ๆ. Idle hours only; productive hours elsewhere are not damage.

ทดสอบตัวเอง

คำถามที่ 1 จาก 3

When is lost profit owed under § 6 (6)?

  • Right.

  • Only in those cases.

  • It is owed in those cases.

คำถามที่ 2 จาก 3

Workers moved to another task during the stop are…

  • Right.

  • No half rate.

  • They were working.

คำถามที่ 3 จาก 3

Idle labour €6,000, idle hire €800, site 10 extra days at €500. Damage?

6,000 + 800 + 5,000 = 11,800.

แหล่งข้อมูลทางการ

ข้อความทางการที่อ่านได้ฟรี บทเรียนอ้างเลขข้อและอธิบายกฎด้วยถ้อยคำของตนเอง