OpenConstruction Academy
Logga in / Registrera
SV

Teori före uppgift 1 · 10 min

Provisional quantities: omit the estimate, add what was built

Mät om de preliminära posterna

Introduktion till kursen

Efter den här lektionen kan du

  1. Say what JBCC PBA clause 26.3 does to work identified as provisional.
  2. Measure rock and fill from joint records the way the bill preamble says: in situ, compacted in place.
  3. Value the adjustment as remeasured quantity less billed quantity, at the bill rate.
1 / 3

Why some quantities are provisional

Below ground the quantity surveyor cannot measure what nobody has seen. Rock in the trenches and unsuitable soil that must be replaced are billed as provisional: an honest estimate, priced at a firm rate, to be remeasured once the work is exposed. Under the JBCC Principal Building Agreement 6.2, clause 26.3, the value of work identified as provisional is omitted and the work as actually executed is added. The rate stays; the quantity changes.

Exempel. A provisional item is not a promise of quantity. Neither side gains or loses from the estimate being wrong; the bill simply follows what was done.
2 / 3

Measure the way the bill was measured

The bill preamble fixes the measurement rules, and the remeasurement must use the same ones. South African bills follow the ASAQS standard system of measuring, and this bill states it plainly: excavation and rock in situ, net as dug, no allowance for bulking; fill compacted in place. Rock is length × trench width × depth of rock, never the full trench depth. Fill is plan area × compacted depth, never the loose volume on the delivery tickets, which includes the bulking that compaction removes.

Exempel. 17.60 m³ delivered loose may compact to 13.50 m³ in place. Only the 13.50 is measured.
Length of rock run14.0 m
Trench width as dug0.7 m
Depth of rock0.4 m
Rock, m³ in situ3.92
3 / 3

The joint record is the evidence

Each measurement comes from a joint record signed by both sides while the work is open. Once the trench is backfilled nobody can check it again, so the record, not memory or an invoice, is what the quantity surveyor measures from. The adjustment for each item is (remeasured − billed quantity) × bill rate. A smaller quantity gives a negative adjustment, which reduces the contract value.

Exempel. Billed 12.00 m³ at R 1,450.00, remeasured 5.32 m³: adjustment −6.68 × 1,450.00.

Remeasure two provisional items

A clinic's foundations are done. Rock and imported fill were billed provisionally. Measure them from the joint records and value the adjustment.

Inte skalenlig
Uppgiften
  • Rock: run 1 is 14.0 m long with 0.4 m of rock; run 2 is 8.0 m long with 0.25 m. Trench width 0.7 m.
  • Fill: one area 9.0 m × 6.0 m, compacted depth 0.25 m. Delivery tickets: 17.6 m³ loose.
  • Bill: rock 12 m³ at R 1,450.00; fill 24 m³ at R 380.00, both provisional.
Steg 1 av 4

Rock in situ

Length × width × depth of rock, for both runs. How many m³ of rock?

14.0 m × 0.7 m × 0.4 m + 8.0 m × 0.7 m × 0.25 m = 5.32 m³.

Steg 2 av 4

Fill compacted in place

Plan area × compacted depth. How many m³ of fill?

9.0 m × 6.0 m × 0.25 m = 13.5 m³, against 17.6 m³ delivered loose.

Steg 3 av 4

Adjustment for rock

(Remeasured − billed) × rate. What is the adjustment for rock?

(5.32 − 12) × R 1,450.00 = −R 9,686.00.

−R 9,6861−R 3,9902?3
  • 1 Rock
  • 2 Fill
  • 3 Adjustment
−R 9,6861−R 3,9902−R 13,6763
  • 1 Rock
  • 2 Fill
  • 3 Adjustment
Steg 4 av 4

Total adjustment

Add the adjustment for fill. What is the total adjustment to the contract value?

−R 9,686.00 + (13.5 − 24) × R 380.00 = −R 13,676.00.

Kort sagt. Omit the provisional quantity, add the measured one, keep the rate. Measure from the joint record by the preamble's rules.

Testa dig själv

Fråga 1 av 3

A trench 22.00 m long and 0.60 m wide has rock 0.35 m deep along its full length; the trench is 0.80 m deep. How many m³ of rock are measured?

22.00 × 0.60 × 0.35 = 4.62 m³ in situ.
Fråga 2 av 3

The fill delivery tickets show more m³ than the compacted volume. Which is measured?

  • Tickets record loose volume. The preamble measures fill compacted in place.

  • Right. Bulking is the contractor's risk in the rate.

  • There is no averaging rule.

Fråga 3 av 3

Under clause 26.3, what happens to a provisional item?

  • That would make it a firm quantity.

  • Right. The rate stays, the quantity follows the work.

  • Cost plus applies to instructed work with no rate to follow, not to provisional quantities.