OpenConstruction Academy
Logga in / Registrera
SV

Introduktion till kursen · 3 min

Betalningsintyg och ändringar (Sydafrika, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

Starta uppgift 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Fiktivt projekt
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
Arbete i ERP
5 uppgifter, cirka 2 h 45 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillUppgift 1
    • Contract instruction CI 03Uppgift 2
    • Contract Data, guarantee optionUppgift 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Uppgift 4
    • Draft for the second certificateUppgift 5
DuQuantity surveyor for the employer

Går från dig

    • Remeasured quantities and the adjustmentUppgift 1
    • Variation order for CI 03Uppgift 2
    • Payment reduction and its releaseUppgift 3
    • Interim payment certificate 1Uppgift 4
    • Certificate 2 with VATUppgift 5
    Principal agentSigns what you value

Din väg genom projektet

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Uppgift 1 · 35 min

    Mät om de preliminära posterna

    Du tar fram
    Remeasured rock and fill, and the adjustment to the bill
    Dokument
    Joint site records, bill preamble
    I ERP
    Bill of Quantities
  2. Value the changes

    Uppgift 2 · 30 min

    Prissätt en kontraktsorder

    Du tar fram
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Dokument
    Contract instruction CI 03 and the bill rates
    I ERP
    Variations
  3. Set the reduction

    Uppgift 3 · 30 min

    Betalningsreduktionen och dess frisläppande

    Du tar fram
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Dokument
    Contract Data D 1.0 and the forecast
    I ERP
    Contracts
  4. Certify

    Uppgift 4 · 35 min

    Betalningsintyg 1

    Du tar fram
    Interim payment certificate 1, net amount certified
    Dokument
    Progress and the materials list
    I ERP
    Contracts
  5. Certify

    Uppgift 5 · 35 min

    Intyg 2: betala inte teglet två gånger

    Du tar fram
    Certificate 2: what the draft overclaims, amount due with VAT
    Dokument
    Contractor's draft for 25 May
    I ERP
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Uppgift 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Uppgift 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Uppgift 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Uppgift 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Uppgift 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.