کورس کا تعارف · 3 منٹ

ادائیگی سرٹیفکیٹس اور ویری ایشنز (جنوبی افریقہ، JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

ٹاسک 1 شروع کریں

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.فرضی پراجیکٹ
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
ERP میں کام
5 ٹاسک، تقریباً 2 گھنٹے 45 منٹ

کون کس کو کیا دیتا ہے

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

آپ کے پاس آتا ہے

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillٹاسک 1
    • Contract instruction CI 03ٹاسک 2
    • Contract Data, guarantee optionٹاسک 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1ٹاسک 4
    • Draft for the second certificateٹاسک 5
آپQuantity surveyor for the employer

آپ سے جاتا ہے

    • Remeasured quantities and the adjustmentٹاسک 1
    • Variation order for CI 03ٹاسک 2
    • Payment reduction and its releaseٹاسک 3
    • Interim payment certificate 1ٹاسک 4
    • Certificate 2 with VATٹاسک 5
    Principal agentSigns what you value

پراجیکٹ میں آپ کا راستہ

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    ٹاسک 1 · 35 منٹ

    عارضی آئٹمز کی دوبارہ پیمائش کریں

    آپ کا نتیجہ
    Remeasured rock and fill, and the adjustment to the bill
    دستاویز
    Joint site records, bill preamble
    ERP میں
    Bill of Quantities
  2. Value the changes

    ٹاسک 2 · 30 منٹ

    ایک کنٹریکٹ ہدایت کی قیمت لگائیں

    آپ کا نتیجہ
    Contract instruction CI 03 valued by clause 26.2 and recorded
    دستاویز
    Contract instruction CI 03 and the bill rates
    ERP میں
    Variations
  3. Set the reduction

    ٹاسک 3 · 30 منٹ

    ادائیگی کٹوتی اور اس کا اجراء

    آپ کا نتیجہ
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    دستاویز
    Contract Data D 1.0 and the forecast
    ERP میں
    Contracts
  4. Certify

    ٹاسک 4 · 35 منٹ

    عبوری ادائیگی سرٹیفکیٹ 1

    آپ کا نتیجہ
    Interim payment certificate 1, net amount certified
    دستاویز
    Progress and the materials list
    ERP میں
    Contracts
  5. Certify

    ٹاسک 5 · 35 منٹ

    سرٹیفکیٹ 2: اینٹوں کی ادائیگی دو بار نہ کریں

    آپ کا نتیجہ
    Certificate 2: what the draft overclaims, amount due with VAT
    دستاویز
    Contractor's draft for 25 May
    ERP میں
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
ٹاسک 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
ٹاسک 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
ٹاسک 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
ٹاسک 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
ٹاسک 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔

مختصراً. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.