کورس کا تعارف · 3 منٹ
ادائیگی سرٹیفکیٹس اور ویری ایشنز (جنوبی افریقہ، JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
فرضی پراجیکٹ- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- ERP میں کام
- 5 ٹاسک، تقریباً 2 گھنٹے 45 منٹ
کون کس کو کیا دیتا ہے
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
آپ کے پاس آتا ہے
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillٹاسک 1
- Contract instruction CI 03ٹاسک 2
- Contract Data, guarantee optionٹاسک 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1ٹاسک 4
- Draft for the second certificateٹاسک 5
آپ سے جاتا ہے
- Remeasured quantities and the adjustmentٹاسک 1
- Variation order for CI 03ٹاسک 2
- Payment reduction and its releaseٹاسک 3
- Interim payment certificate 1ٹاسک 4
- Certificate 2 with VATٹاسک 5
پراجیکٹ میں آپ کا راستہ
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
ٹاسک 1 · 35 منٹ
عارضی آئٹمز کی دوبارہ پیمائش کریں
- آپ کا نتیجہ
- Remeasured rock and fill, and the adjustment to the bill
- دستاویز
- Joint site records, bill preamble
- ERP میں
- Bill of Quantities
Value the changes
ٹاسک 2 · 30 منٹ
ایک کنٹریکٹ ہدایت کی قیمت لگائیں
- آپ کا نتیجہ
- Contract instruction CI 03 valued by clause 26.2 and recorded
- دستاویز
- Contract instruction CI 03 and the bill rates
- ERP میں
- Variations
Set the reduction
ٹاسک 3 · 30 منٹ
ادائیگی کٹوتی اور اس کا اجراء
- آپ کا نتیجہ
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- دستاویز
- Contract Data D 1.0 and the forecast
- ERP میں
- Contracts
Certify
ٹاسک 4 · 35 منٹ
عبوری ادائیگی سرٹیفکیٹ 1
- آپ کا نتیجہ
- Interim payment certificate 1, net amount certified
- دستاویز
- Progress and the materials list
- ERP میں
- Contracts
Certify
ٹاسک 5 · 35 منٹ
سرٹیفکیٹ 2: اینٹوں کی ادائیگی دو بار نہ کریں
- آپ کا نتیجہ
- Certificate 2: what the draft overclaims, amount due with VAT
- دستاویز
- Contractor's draft for 25 May
- ERP میں
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔
مختصراً. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.