Kurssin johdanto · 3 min
Maksutodistukset ja muutostyöt (Etelä-Afrikka, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Kuvitteellinen hanke- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Työ ERP:ssä
- Tehtäviä 5, noin 2 t 45 min
Kuka antaa mitä kenelle
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tulee sinulle
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillTehtävä 1
- Contract instruction CI 03Tehtävä 2
- Contract Data, guarantee optionTehtävä 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Tehtävä 4
- Draft for the second certificateTehtävä 5
Lähtee sinulta
- Remeasured quantities and the adjustmentTehtävä 1
- Variation order for CI 03Tehtävä 2
- Payment reduction and its releaseTehtävä 3
- Interim payment certificate 1Tehtävä 4
- Certificate 2 with VATTehtävä 5
Reittisi hankkeen läpi
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Tehtävä 1 · 35 min
Arviomääräisten nimikkeiden uudelleenmittaus
- Tuotat
- Remeasured rock and fill, and the adjustment to the bill
- Asiakirja
- Joint site records, bill preamble
- ERP:ssä
- Bill of Quantities
Value the changes
Tehtävä 2 · 30 min
Sopimusmääräyksen hinnoittelu
- Tuotat
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Asiakirja
- Contract instruction CI 03 and the bill rates
- ERP:ssä
- Variations
Set the reduction
Tehtävä 3 · 30 min
Maksunvähennys ja sen vapautuminen
- Tuotat
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Asiakirja
- Contract Data D 1.0 and the forecast
- ERP:ssä
- Contracts
Certify
Tehtävä 4 · 35 min
Väliaikainen maksutodistus 1
- Tuotat
- Interim payment certificate 1, net amount certified
- Asiakirja
- Progress and the materials list
- ERP:ssä
- Contracts
Certify
Tehtävä 5 · 35 min
Todistus 2: älä maksa tiilistä kahdesti
- Tuotat
- Certificate 2: what the draft overclaims, amount due with VAT
- Asiakirja
- Contractor's draft for 25 May
- ERP:ssä
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.