OpenConstruction Academy
ورود / ثبت‌نام
FA

معرفی دوره · 3 دقیقه

گواهی‌های پرداخت و تغییرات (آفریقای جنوبی، JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

شروع تکلیف 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.پروژهٔ خیالی
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
کار در ERP
5 تکلیف، حدود 2 ساعت 45 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillتکلیف 1
    • Contract instruction CI 03تکلیف 2
    • Contract Data, guarantee optionتکلیف 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1تکلیف 4
    • Draft for the second certificateتکلیف 5
شماQuantity surveyor for the employer

از شما می‌رود

    • Remeasured quantities and the adjustmentتکلیف 1
    • Variation order for CI 03تکلیف 2
    • Payment reduction and its releaseتکلیف 3
    • Interim payment certificate 1تکلیف 4
    • Certificate 2 with VATتکلیف 5
    Principal agentSigns what you value

مسیر شما در پروژه

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    تکلیف 1 · 35 دقیقه

    اقلام موقت را دوباره اندازه‌گیری کنید

    خروجی شما
    Remeasured rock and fill, and the adjustment to the bill
    سند
    Joint site records, bill preamble
    در ERP
    Bill of Quantities
  2. Value the changes

    تکلیف 2 · 30 دقیقه

    یک دستور قرارداد را قیمت‌گذاری کنید

    خروجی شما
    Contract instruction CI 03 valued by clause 26.2 and recorded
    سند
    Contract instruction CI 03 and the bill rates
    در ERP
    Variations
  3. Set the reduction

    تکلیف 3 · 30 دقیقه

    کسر پرداخت و آزادسازی آن

    خروجی شما
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    سند
    Contract Data D 1.0 and the forecast
    در ERP
    Contracts
  4. Certify

    تکلیف 4 · 35 دقیقه

    گواهی پرداخت موقت 1

    خروجی شما
    Interim payment certificate 1, net amount certified
    سند
    Progress and the materials list
    در ERP
    Contracts
  5. Certify

    تکلیف 5 · 35 دقیقه

    گواهی 2: بهای آجرها را دو بار نپردازید

    خروجی شما
    Certificate 2: what the draft overclaims, amount due with VAT
    سند
    Contractor's draft for 25 May
    در ERP
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
تکلیف 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
تکلیف 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
تکلیف 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
تکلیف 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
تکلیف 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.