معرفی دوره · 3 دقیقه
گواهیهای پرداخت و تغییرات (آفریقای جنوبی، JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
پروژهٔ خیالی- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- کار در ERP
- 5 تکلیف، حدود 2 ساعت 45 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillتکلیف 1
- Contract instruction CI 03تکلیف 2
- Contract Data, guarantee optionتکلیف 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1تکلیف 4
- Draft for the second certificateتکلیف 5
از شما میرود
- Remeasured quantities and the adjustmentتکلیف 1
- Variation order for CI 03تکلیف 2
- Payment reduction and its releaseتکلیف 3
- Interim payment certificate 1تکلیف 4
- Certificate 2 with VATتکلیف 5
مسیر شما در پروژه
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
تکلیف 1 · 35 دقیقه
اقلام موقت را دوباره اندازهگیری کنید
- خروجی شما
- Remeasured rock and fill, and the adjustment to the bill
- سند
- Joint site records, bill preamble
- در ERP
- Bill of Quantities
Value the changes
تکلیف 2 · 30 دقیقه
یک دستور قرارداد را قیمتگذاری کنید
- خروجی شما
- Contract instruction CI 03 valued by clause 26.2 and recorded
- سند
- Contract instruction CI 03 and the bill rates
- در ERP
- Variations
Set the reduction
تکلیف 3 · 30 دقیقه
کسر پرداخت و آزادسازی آن
- خروجی شما
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- سند
- Contract Data D 1.0 and the forecast
- در ERP
- Contracts
Certify
تکلیف 4 · 35 دقیقه
گواهی پرداخت موقت 1
- خروجی شما
- Interim payment certificate 1, net amount certified
- سند
- Progress and the materials list
- در ERP
- Contracts
Certify
تکلیف 5 · 35 دقیقه
گواهی 2: بهای آجرها را دو بار نپردازید
- خروجی شما
- Certificate 2: what the draft overclaims, amount due with VAT
- سند
- Contractor's draft for 25 May
- در ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.