Въведение в курса · 3 мин
Платежни сертификати и промени (Южна Африка, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Измислен проект- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Работа в ERP
- Задачи: 5, около 2 ч 45 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillЗадача 1
- Contract instruction CI 03Задача 2
- Contract Data, guarantee optionЗадача 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Задача 4
- Draft for the second certificateЗадача 5
Тръгва от вас
- Remeasured quantities and the adjustmentЗадача 1
- Variation order for CI 03Задача 2
- Payment reduction and its releaseЗадача 3
- Interim payment certificate 1Задача 4
- Certificate 2 with VATЗадача 5
Вашият път през проекта
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Задача 1 · 35 мин
Пре-измерване на условните позиции
- Вашият резултат
- Remeasured rock and fill, and the adjustment to the bill
- Документ
- Joint site records, bill preamble
- В ERP
- Bill of Quantities
Value the changes
Задача 2 · 30 мин
Остойностяване на нареждане по договора
- Вашият резултат
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Документ
- Contract instruction CI 03 and the bill rates
- В ERP
- Variations
Set the reduction
Задача 3 · 30 мин
Намалението на плащането и неговото връщане
- Вашият резултат
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Документ
- Contract Data D 1.0 and the forecast
- В ERP
- Contracts
Certify
Задача 4 · 35 мин
Междинен платежен сертификат 1
- Вашият резултат
- Interim payment certificate 1, net amount certified
- Документ
- Progress and the materials list
- В ERP
- Contracts
Certify
Задача 5 · 35 мин
Сертификат 2: не плащайте тухлите два пъти
- Вашият резултат
- Certificate 2: what the draft overclaims, amount due with VAT
- Документ
- Contractor's draft for 25 May
- В ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.