Betalingsattester og ekstraarbejder (Sydafrika, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Fiktivt projekt- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Arbejde i ERP
- 5 opgaver, cirka 2 t 45 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillOpgave 1
- Contract instruction CI 03Opgave 2
- Contract Data, guarantee optionOpgave 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Opgave 4
- Draft for the second certificateOpgave 5
Går fra dig
- Remeasured quantities and the adjustmentOpgave 1
- Variation order for CI 03Opgave 2
- Payment reduction and its releaseOpgave 3
- Interim payment certificate 1Opgave 4
- Certificate 2 with VATOpgave 5
Din vej gennem sagen
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Opgave 1 · 35 min
Genopmål de foreløbige poster
- Du leverer
- Remeasured rock and fill, and the adjustment to the bill
- Dokument
- Joint site records, bill preamble
- I ERP
- Bill of Quantities
Value the changes
Opgave 2 · 30 min
Prissæt en kontraktinstruks
- Du leverer
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Dokument
- Contract instruction CI 03 and the bill rates
- I ERP
- Variations
Set the reduction
Opgave 3 · 30 min
Betalingsreduktionen og dens frigivelse
- Du leverer
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Dokument
- Contract Data D 1.0 and the forecast
- I ERP
- Contracts
Certify
Opgave 4 · 35 min
Løbende betalingsattest 1
- Du leverer
- Interim payment certificate 1, net amount certified
- Dokument
- Progress and the materials list
- I ERP
- Contracts
Certify
Opgave 5 · 35 min
Attest 2: betal ikke for murstenene to gange
- Du leverer
- Certificate 2: what the draft overclaims, amount due with VAT
- Dokument
- Contractor's draft for 25 May
- I ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.