Panimula ng kurso · 3 min
Mga payment certificate at variation (South Africa, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Kathang-isip na proyekto- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Trabaho sa ERP
- 5 gawain, mga 2 oras 45 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillGawain 1
- Contract instruction CI 03Gawain 2
- Contract Data, guarantee optionGawain 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Gawain 4
- Draft for the second certificateGawain 5
Lumalabas sa iyo
- Remeasured quantities and the adjustmentGawain 1
- Variation order for CI 03Gawain 2
- Payment reduction and its releaseGawain 3
- Interim payment certificate 1Gawain 4
- Certificate 2 with VATGawain 5
Ang ruta mo sa proyekto
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Gawain 1 · 35 min
I-remeasure ang mga provisional na item
- Ang gagawin mo
- Remeasured rock and fill, and the adjustment to the bill
- Dokumento
- Joint site records, bill preamble
- Sa ERP
- Bill of Quantities
Value the changes
Gawain 2 · 30 min
Ipresyo ang isang contract instruction
- Ang gagawin mo
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Dokumento
- Contract instruction CI 03 and the bill rates
- Sa ERP
- Variations
Set the reduction
Gawain 3 · 30 min
Ang payment reduction at ang paglabas nito
- Ang gagawin mo
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Dokumento
- Contract Data D 1.0 and the forecast
- Sa ERP
- Contracts
Certify
Gawain 4 · 35 min
Interim payment certificate 1
- Ang gagawin mo
- Interim payment certificate 1, net amount certified
- Dokumento
- Progress and the materials list
- Sa ERP
- Contracts
Certify
Gawain 5 · 35 min
Certificate 2: huwag bayaran nang dalawang beses ang mga brick
- Ang gagawin mo
- Certificate 2: what the draft overclaims, amount due with VAT
- Dokumento
- Contractor's draft for 25 May
- Sa ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.