Panimula ng kurso · 3 min

Mga payment certificate at variation (South Africa, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

Simulan ang gawain 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Kathang-isip na proyekto
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
Trabaho sa ERP
5 gawain, mga 2 oras 45 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillGawain 1
    • Contract instruction CI 03Gawain 2
    • Contract Data, guarantee optionGawain 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Gawain 4
    • Draft for the second certificateGawain 5
IkawQuantity surveyor for the employer

Lumalabas sa iyo

    • Remeasured quantities and the adjustmentGawain 1
    • Variation order for CI 03Gawain 2
    • Payment reduction and its releaseGawain 3
    • Interim payment certificate 1Gawain 4
    • Certificate 2 with VATGawain 5
    Principal agentSigns what you value

Ang ruta mo sa proyekto

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Gawain 1 · 35 min

    I-remeasure ang mga provisional na item

    Ang gagawin mo
    Remeasured rock and fill, and the adjustment to the bill
    Dokumento
    Joint site records, bill preamble
    Sa ERP
    Bill of Quantities
  2. Value the changes

    Gawain 2 · 30 min

    Ipresyo ang isang contract instruction

    Ang gagawin mo
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Dokumento
    Contract instruction CI 03 and the bill rates
    Sa ERP
    Variations
  3. Set the reduction

    Gawain 3 · 30 min

    Ang payment reduction at ang paglabas nito

    Ang gagawin mo
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Dokumento
    Contract Data D 1.0 and the forecast
    Sa ERP
    Contracts
  4. Certify

    Gawain 4 · 35 min

    Interim payment certificate 1

    Ang gagawin mo
    Interim payment certificate 1, net amount certified
    Dokumento
    Progress and the materials list
    Sa ERP
    Contracts
  5. Certify

    Gawain 5 · 35 min

    Certificate 2: huwag bayaran nang dalawang beses ang mga brick

    Ang gagawin mo
    Certificate 2: what the draft overclaims, amount due with VAT
    Dokumento
    Contractor's draft for 25 May
    Sa ERP
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Gawain 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Gawain 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Gawain 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Gawain 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Gawain 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.