Сургалтын танилцуулга · 3 мин
Төлбөрийн гэрчилгээ ба өөрчлөлтүүд (Өмнөд Африк, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Зохиомол төсөл- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 2 цаг 45 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillДаалгавар 1
- Contract instruction CI 03Даалгавар 2
- Contract Data, guarantee optionДаалгавар 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Даалгавар 4
- Draft for the second certificateДаалгавар 5
Танаас гардаг
- Remeasured quantities and the adjustmentДаалгавар 1
- Variation order for CI 03Даалгавар 2
- Payment reduction and its releaseДаалгавар 3
- Interim payment certificate 1Даалгавар 4
- Certificate 2 with VATДаалгавар 5
Төслөөр явах таны зам
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Даалгавар 1 · 35 мин
Түр байрлалуудыг дахин хэмжих
- Үр дүн
- Remeasured rock and fill, and the adjustment to the bill
- Баримт бичиг
- Joint site records, bill preamble
- ERP дээр
- Bill of Quantities
Value the changes
Даалгавар 2 · 30 мин
Гэрээний зааврыг үнэлэх
- Үр дүн
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Баримт бичиг
- Contract instruction CI 03 and the bill rates
- ERP дээр
- Variations
Set the reduction
Даалгавар 3 · 30 мин
Төлбөрийн бууралт ба түүний чөлөөлөлт
- Үр дүн
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Баримт бичиг
- Contract Data D 1.0 and the forecast
- ERP дээр
- Contracts
Certify
Даалгавар 4 · 35 мин
1-р завсрын төлбөрийн гэрчилгээ
- Үр дүн
- Interim payment certificate 1, net amount certified
- Баримт бичиг
- Progress and the materials list
- ERP дээр
- Contracts
Certify
Даалгавар 5 · 35 мин
Гэрчилгээ 2: тоосгыг хоёр удаа төлөхгүй
- Үр дүн
- Certificate 2: what the draft overclaims, amount due with VAT
- Баримт бичиг
- Contractor's draft for 25 May
- ERP дээр
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.