You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

1-р даалгаврыг эхлэх

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Зохиомол төсөл
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 2 цаг 45 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillДаалгавар 1
    • Contract instruction CI 03Даалгавар 2
    • Contract Data, guarantee optionДаалгавар 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Даалгавар 4
    • Draft for the second certificateДаалгавар 5
ТаQuantity surveyor for the employer

Танаас гардаг

    • Remeasured quantities and the adjustmentДаалгавар 1
    • Variation order for CI 03Даалгавар 2
    • Payment reduction and its releaseДаалгавар 3
    • Interim payment certificate 1Даалгавар 4
    • Certificate 2 with VATДаалгавар 5
    Principal agentSigns what you value

Төслөөр явах таны зам

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Даалгавар 1 · 35 мин

    Түр байрлалуудыг дахин хэмжих

    Үр дүн
    Remeasured rock and fill, and the adjustment to the bill
    Баримт бичиг
    Joint site records, bill preamble
    ERP дээр
    Bill of Quantities
  2. Value the changes

    Даалгавар 2 · 30 мин

    Гэрээний зааврыг үнэлэх

    Үр дүн
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Баримт бичиг
    Contract instruction CI 03 and the bill rates
    ERP дээр
    Variations
  3. Set the reduction

    Даалгавар 3 · 30 мин

    Төлбөрийн бууралт ба түүний чөлөөлөлт

    Үр дүн
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Баримт бичиг
    Contract Data D 1.0 and the forecast
    ERP дээр
    Contracts
  4. Certify

    Даалгавар 4 · 35 мин

    1-р завсрын төлбөрийн гэрчилгээ

    Үр дүн
    Interim payment certificate 1, net amount certified
    Баримт бичиг
    Progress and the materials list
    ERP дээр
    Contracts
  5. Certify

    Даалгавар 5 · 35 мин

    Гэрчилгээ 2: тоосгыг хоёр удаа төлөхгүй

    Үр дүн
    Certificate 2: what the draft overclaims, amount due with VAT
    Баримт бичиг
    Contractor's draft for 25 May
    ERP дээр
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Даалгавар 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Даалгавар 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Даалгавар 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Даалгавар 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Даалгавар 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.