Курсқа кіріспе · 3 мин

Төлем сертификаттары және өзгерістер (Оңтүстік Африка, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

1-тапсырманы бастау

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Ойдан шығарылған жоба
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
ERP-дегі жұмыс
Тапсырмалар: 5, шамамен 2 сағ 45 мин

Кім кімге не береді

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сізге келеді

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fill1-тапсырма
    • Contract instruction CI 032-тапсырма
    • Contract Data, guarantee option3-тапсырма
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 14-тапсырма
    • Draft for the second certificate5-тапсырма
СізQuantity surveyor for the employer

Сізден кетеді

    • Remeasured quantities and the adjustment1-тапсырма
    • Variation order for CI 032-тапсырма
    • Payment reduction and its release3-тапсырма
    • Interim payment certificate 14-тапсырма
    • Certificate 2 with VAT5-тапсырма
    Principal agentSigns what you value

Жоба бойынша жолыңыз

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    1-тапсырма · 35 мин

    Алдын ала позицияларды қайта өлшеу

    Нәтиже
    Remeasured rock and fill, and the adjustment to the bill
    Құжат
    Joint site records, bill preamble
    ERP-де
    Bill of Quantities
  2. Value the changes

    2-тапсырма · 30 мин

    Келісімшарттық нұсқауды бағалау

    Нәтиже
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Құжат
    Contract instruction CI 03 and the bill rates
    ERP-де
    Variations
  3. Set the reduction

    3-тапсырма · 30 мин

    Төлемді азайту және оны босату

    Нәтиже
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Құжат
    Contract Data D 1.0 and the forecast
    ERP-де
    Contracts
  4. Certify

    4-тапсырма · 35 мин

    Аралық төлем сертификаты 1

    Нәтиже
    Interim payment certificate 1, net amount certified
    Құжат
    Progress and the materials list
    ERP-де
    Contracts
  5. Certify

    5-тапсырма · 35 мин

    2-сертификат: кірпішке екі рет төлемеңіз

    Нәтиже
    Certificate 2: what the draft overclaims, amount due with VAT
    Құжат
    Contractor's draft for 25 May
    ERP-де
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
1-тапсырмаMeasure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
2-тапсырмаValue an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
3-тапсырмаHold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
4-тапсырмаCertificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
5-тапсырмаCertificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.

Қысқаша. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.