Курсқа кіріспе · 3 мин
Төлем сертификаттары және өзгерістер (Оңтүстік Африка, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Ойдан шығарылған жоба- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- ERP-дегі жұмыс
- Тапсырмалар: 5, шамамен 2 сағ 45 мин
Кім кімге не береді
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сізге келеді
- Principal agentIssues instructions and certificates
- Joint site records of rock and fill1-тапсырма
- Contract instruction CI 032-тапсырма
- Contract Data, guarantee option3-тапсырма
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 14-тапсырма
- Draft for the second certificate5-тапсырма
Сізден кетеді
- Remeasured quantities and the adjustment1-тапсырма
- Variation order for CI 032-тапсырма
- Payment reduction and its release3-тапсырма
- Interim payment certificate 14-тапсырма
- Certificate 2 with VAT5-тапсырма
Жоба бойынша жолыңыз
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
1-тапсырма · 35 мин
Алдын ала позицияларды қайта өлшеу
- Нәтиже
- Remeasured rock and fill, and the adjustment to the bill
- Құжат
- Joint site records, bill preamble
- ERP-де
- Bill of Quantities
Value the changes
2-тапсырма · 30 мин
Келісімшарттық нұсқауды бағалау
- Нәтиже
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Құжат
- Contract instruction CI 03 and the bill rates
- ERP-де
- Variations
Set the reduction
3-тапсырма · 30 мин
Төлемді азайту және оны босату
- Нәтиже
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Құжат
- Contract Data D 1.0 and the forecast
- ERP-де
- Contracts
Certify
4-тапсырма · 35 мин
Аралық төлем сертификаты 1
- Нәтиже
- Interim payment certificate 1, net amount certified
- Құжат
- Progress and the materials list
- ERP-де
- Contracts
Certify
5-тапсырма · 35 мин
2-сертификат: кірпішке екі рет төлемеңіз
- Нәтиже
- Certificate 2: what the draft overclaims, amount due with VAT
- Құжат
- Contractor's draft for 25 May
- ERP-де
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.
Қысқаша. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.