Inleiding tot de cursus · 3 min
Betalingscertificaten en meerwerken (Zuid-Afrika, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Fictief project- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Werk in de ERP
- 5 opdrachten, ongeveer 2 u 45 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillOpdracht 1
- Contract instruction CI 03Opdracht 2
- Contract Data, guarantee optionOpdracht 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Opdracht 4
- Draft for the second certificateOpdracht 5
Gaat van u uit
- Remeasured quantities and the adjustmentOpdracht 1
- Variation order for CI 03Opdracht 2
- Payment reduction and its releaseOpdracht 3
- Interim payment certificate 1Opdracht 4
- Certificate 2 with VATOpdracht 5
Uw route door het project
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Opdracht 1 · 35 min
De voorlopige posten opnieuw opmeten
- U levert
- Remeasured rock and fill, and the adjustment to the bill
- Document
- Joint site records, bill preamble
- In de ERP
- Bill of Quantities
Value the changes
Opdracht 2 · 30 min
Een contractinstructie prijzen
- U levert
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Document
- Contract instruction CI 03 and the bill rates
- In de ERP
- Variations
Set the reduction
Opdracht 3 · 30 min
De betalingsinhouding (payment reduction) en de vrijgave ervan
- U levert
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Document
- Contract Data D 1.0 and the forecast
- In de ERP
- Contracts
Certify
Opdracht 4 · 35 min
Tussentijds betalingscertificaat 1
- U levert
- Interim payment certificate 1, net amount certified
- Document
- Progress and the materials list
- In de ERP
- Contracts
Certify
Opdracht 5 · 35 min
Certificaat 2: betaal de stenen niet twee keer
- U levert
- Certificate 2: what the draft overclaims, amount due with VAT
- Document
- Contractor's draft for 25 May
- In de ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.