Uvod u tečaj · 3 min
Potvrde o plaćanju i izmjene ugovora (Južna Afrika, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Izmišljeni projekt- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Rad u ERP-u
- Zadataka: 5, oko 2 h 45 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillZadatak 1
- Contract instruction CI 03Zadatak 2
- Contract Data, guarantee optionZadatak 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Zadatak 4
- Draft for the second certificateZadatak 5
Odlazi od vas
- Remeasured quantities and the adjustmentZadatak 1
- Variation order for CI 03Zadatak 2
- Payment reduction and its releaseZadatak 3
- Interim payment certificate 1Zadatak 4
- Certificate 2 with VATZadatak 5
Vaš put kroz projekt
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Zadatak 1 · 35 min
Ponovno izmjerite privremene stavke
- Vaš rezultat
- Remeasured rock and fill, and the adjustment to the bill
- Dokument
- Joint site records, bill preamble
- U ERP-u
- Bill of Quantities
Value the changes
Zadatak 2 · 30 min
Cijenite ugovornu uputu
- Vaš rezultat
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Dokument
- Contract instruction CI 03 and the bill rates
- U ERP-u
- Variations
Set the reduction
Zadatak 3 · 30 min
Smanjenje plaćanja i njegovo oslobađanje
- Vaš rezultat
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Dokument
- Contract Data D 1.0 and the forecast
- U ERP-u
- Contracts
Certify
Zadatak 4 · 35 min
Privremena potvrda o plaćanju 1
- Vaš rezultat
- Interim payment certificate 1, net amount certified
- Dokument
- Progress and the materials list
- U ERP-u
- Contracts
Certify
Zadatak 5 · 35 min
Potvrda 2: ne plaćajte opeku dvaput
- Vaš rezultat
- Certificate 2: what the draft overclaims, amount due with VAT
- Dokument
- Contractor's draft for 25 May
- U ERP-u
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.