Potvrde o plaćanju i izmjene ugovora (Južna Afrika, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

Započni zadatak 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Izmišljeni projekt
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
Rad u ERP-u
Zadataka: 5, oko 2 h 45 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillZadatak 1
    • Contract instruction CI 03Zadatak 2
    • Contract Data, guarantee optionZadatak 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Zadatak 4
    • Draft for the second certificateZadatak 5
ViQuantity surveyor for the employer

Odlazi od vas

    • Remeasured quantities and the adjustmentZadatak 1
    • Variation order for CI 03Zadatak 2
    • Payment reduction and its releaseZadatak 3
    • Interim payment certificate 1Zadatak 4
    • Certificate 2 with VATZadatak 5
    Principal agentSigns what you value

Vaš put kroz projekt

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Zadatak 1 · 35 min

    Ponovno izmjerite privremene stavke

    Vaš rezultat
    Remeasured rock and fill, and the adjustment to the bill
    Dokument
    Joint site records, bill preamble
    U ERP-u
    Bill of Quantities
  2. Value the changes

    Zadatak 2 · 30 min

    Cijenite ugovornu uputu

    Vaš rezultat
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Dokument
    Contract instruction CI 03 and the bill rates
    U ERP-u
    Variations
  3. Set the reduction

    Zadatak 3 · 30 min

    Smanjenje plaćanja i njegovo oslobađanje

    Vaš rezultat
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Dokument
    Contract Data D 1.0 and the forecast
    U ERP-u
    Contracts
  4. Certify

    Zadatak 4 · 35 min

    Privremena potvrda o plaćanju 1

    Vaš rezultat
    Interim payment certificate 1, net amount certified
    Dokument
    Progress and the materials list
    U ERP-u
    Contracts
  5. Certify

    Zadatak 5 · 35 min

    Potvrda 2: ne plaćajte opeku dvaput

    Vaš rezultat
    Certificate 2: what the draft overclaims, amount due with VAT
    Dokument
    Contractor's draft for 25 May
    U ERP-u
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Zadatak 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Zadatak 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Zadatak 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Zadatak 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Zadatak 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.