Úvod do kurzu · 3 min
Platební certifikáty a změny (Jižní Afrika, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Smyšlený projekt- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Práce v ERP
- Úlohy: 5, asi 2 h 45 min
Kdo komu co předává
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillÚloha 1
- Contract instruction CI 03Úloha 2
- Contract Data, guarantee optionÚloha 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Úloha 4
- Draft for the second certificateÚloha 5
Odchází od vás
- Remeasured quantities and the adjustmentÚloha 1
- Variation order for CI 03Úloha 2
- Payment reduction and its releaseÚloha 3
- Interim payment certificate 1Úloha 4
- Certificate 2 with VATÚloha 5
Vaše cesta zakázkou
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Úloha 1 · 35 min
Nové zaměření orientačních položek
- Výstup
- Remeasured rock and fill, and the adjustment to the bill
- Dokument
- Joint site records, bill preamble
- V ERP
- Bill of Quantities
Value the changes
Úloha 2 · 30 min
Ocenění smluvního pokynu
- Výstup
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Dokument
- Contract instruction CI 03 and the bill rates
- V ERP
- Variations
Set the reduction
Úloha 3 · 30 min
Srážka z platby (payment reduction) a její uvolnění
- Výstup
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Dokument
- Contract Data D 1.0 and the forecast
- V ERP
- Contracts
Certify
Úloha 4 · 35 min
Průběžný platební certifikát 1
- Výstup
- Interim payment certificate 1, net amount certified
- Dokument
- Progress and the materials list
- V ERP
- Contracts
Certify
Úloha 5 · 35 min
Certifikát 2: neplať cihly dvakrát
- Výstup
- Certificate 2: what the draft overclaims, amount due with VAT
- Dokument
- Contractor's draft for 25 May
- V ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.