Төлөм күбөлүктөрү жана өзгөртүүлөр (Түштүк Африка, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

1-тапшырманы баштоо

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Ойдон чыгарылган долбоор
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
ERPдеги иш
Тапшырмалар: 5, болжол менен 2 саат 45 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fill1-тапшырма
    • Contract instruction CI 032-тапшырма
    • Contract Data, guarantee option3-тапшырма
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 14-тапшырма
    • Draft for the second certificate5-тапшырма
СизQuantity surveyor for the employer

Сизден кетет

    • Remeasured quantities and the adjustment1-тапшырма
    • Variation order for CI 032-тапшырма
    • Payment reduction and its release3-тапшырма
    • Interim payment certificate 14-тапшырма
    • Certificate 2 with VAT5-тапшырма
    Principal agentSigns what you value

Долбоор боюнча жолуңуз

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    1-тапшырма · 35 мүн

    Убактылуу позицияларды кайра өлчөө

    Натыйжа
    Remeasured rock and fill, and the adjustment to the bill
    Документ
    Joint site records, bill preamble
    ERPде
    Bill of Quantities
  2. Value the changes

    2-тапшырма · 30 мүн

    Келишим боюнча көрсөтмөнү баалоо

    Натыйжа
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Документ
    Contract instruction CI 03 and the bill rates
    ERPде
    Variations
  3. Set the reduction

    3-тапшырма · 30 мүн

    Төлөмдү кыскартуу жана аны бошотуу

    Натыйжа
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Документ
    Contract Data D 1.0 and the forecast
    ERPде
    Contracts
  4. Certify

    4-тапшырма · 35 мүн

    1-аралык төлөм күбөлүгү

    Натыйжа
    Interim payment certificate 1, net amount certified
    Документ
    Progress and the materials list
    ERPде
    Contracts
  5. Certify

    5-тапшырма · 35 мүн

    2-күбөлүк: кирпичке эки жолу төлөбө

    Натыйжа
    Certificate 2: what the draft overclaims, amount due with VAT
    Документ
    Contractor's draft for 25 May
    ERPде
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
1-тапшырмаMeasure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
2-тапшырмаValue an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
3-тапшырмаHold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
4-тапшырмаCertificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
5-тапшырмаCertificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.