Курска киришүү · 3 мүн
Төлөм күбөлүктөрү жана өзгөртүүлөр (Түштүк Африка, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Ойдон чыгарылган долбоор- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 2 саат 45 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Principal agentIssues instructions and certificates
- Joint site records of rock and fill1-тапшырма
- Contract instruction CI 032-тапшырма
- Contract Data, guarantee option3-тапшырма
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 14-тапшырма
- Draft for the second certificate5-тапшырма
Сизден кетет
- Remeasured quantities and the adjustment1-тапшырма
- Variation order for CI 032-тапшырма
- Payment reduction and its release3-тапшырма
- Interim payment certificate 14-тапшырма
- Certificate 2 with VAT5-тапшырма
Долбоор боюнча жолуңуз
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
1-тапшырма · 35 мүн
Убактылуу позицияларды кайра өлчөө
- Натыйжа
- Remeasured rock and fill, and the adjustment to the bill
- Документ
- Joint site records, bill preamble
- ERPде
- Bill of Quantities
Value the changes
2-тапшырма · 30 мүн
Келишим боюнча көрсөтмөнү баалоо
- Натыйжа
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Документ
- Contract instruction CI 03 and the bill rates
- ERPде
- Variations
Set the reduction
3-тапшырма · 30 мүн
Төлөмдү кыскартуу жана аны бошотуу
- Натыйжа
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Документ
- Contract Data D 1.0 and the forecast
- ERPде
- Contracts
Certify
4-тапшырма · 35 мүн
1-аралык төлөм күбөлүгү
- Натыйжа
- Interim payment certificate 1, net amount certified
- Документ
- Progress and the materials list
- ERPде
- Contracts
Certify
5-тапшырма · 35 мүн
2-күбөлүк: кирпичке эки жолу төлөбө
- Натыйжа
- Certificate 2: what the draft overclaims, amount due with VAT
- Документ
- Contractor's draft for 25 May
- ERPде
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.