מבוא לקורס · 3 דק׳
תעודות תשלום ושינויים (דרום אפריקה, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
פרויקט בדיוני- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- עבודה ב-ERP
- 5 משימות, כ-2 ש׳ 45 דק׳
מי מעביר מה למי
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
מגיע אליכם
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillמשימה 1
- Contract instruction CI 03משימה 2
- Contract Data, guarantee optionמשימה 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1משימה 4
- Draft for the second certificateמשימה 5
יוצא מכם
- Remeasured quantities and the adjustmentמשימה 1
- Variation order for CI 03משימה 2
- Payment reduction and its releaseמשימה 3
- Interim payment certificate 1משימה 4
- Certificate 2 with VATמשימה 5
המסלול שלכם בפרויקט
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
משימה 1 · 35 דק׳
מדידה מחדש של הסעיפים הזמניים
- התוצר שלכם
- Remeasured rock and fill, and the adjustment to the bill
- מסמך
- Joint site records, bill preamble
- ב-ERP
- Bill of Quantities
Value the changes
משימה 2 · 30 דק׳
תמחור הוראת חוזה (contract instruction)
- התוצר שלכם
- Contract instruction CI 03 valued by clause 26.2 and recorded
- מסמך
- Contract instruction CI 03 and the bill rates
- ב-ERP
- Variations
Set the reduction
משימה 3 · 30 דק׳
הפחתת התשלום ושחרורה
- התוצר שלכם
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- מסמך
- Contract Data D 1.0 and the forecast
- ב-ERP
- Contracts
Certify
משימה 4 · 35 דק׳
תעודת תשלום ביניים 1
- התוצר שלכם
- Interim payment certificate 1, net amount certified
- מסמך
- Progress and the materials list
- ב-ERP
- Contracts
Certify
משימה 5 · 35 דק׳
תעודה 2: אל תשלמו על הלבנים פעמיים
- התוצר שלכם
- Certificate 2: what the draft overclaims, amount due with VAT
- מסמך
- Contractor's draft for 25 May
- ב-ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.
בקצרה. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.