Course introduction · 3 min
Payment certificates and variations (South Africa, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Fictional project- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Work in the ERP
- 5 tasks, about 2 h 45 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillTask 1
- Contract instruction CI 03Task 2
- Contract Data, guarantee optionTask 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Task 4
- Draft for the second certificateTask 5
Goes from you
- Remeasured quantities and the adjustmentTask 1
- Variation order for CI 03Task 2
- Payment reduction and its releaseTask 3
- Interim payment certificate 1Task 4
- Certificate 2 with VATTask 5
Your route through the job
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Task 1 · 35 min
Remeasure the provisional items
- You produce
- Remeasured rock and fill, and the adjustment to the bill
- Document
- Joint site records, bill preamble
- In the ERP
- Bill of Quantities
Value the changes
Task 2 · 30 min
Price a contract instruction
- You produce
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Document
- Contract instruction CI 03 and the bill rates
- In the ERP
- Variations
Set the reduction
Task 3 · 30 min
The payment reduction and its release
- You produce
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Document
- Contract Data D 1.0 and the forecast
- In the ERP
- Contracts
Certify
Task 4 · 35 min
Interim payment certificate 1
- You produce
- Interim payment certificate 1, net amount certified
- Document
- Progress and the materials list
- In the ERP
- Contracts
Certify
Task 5 · 35 min
Certificate 2: do not pay the bricks twice
- You produce
- Certificate 2: what the draft overclaims, amount due with VAT
- Document
- Contractor's draft for 25 May
- In the ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Blue is what the task adds; grey is carried over from before.
In short. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.