Course introduction · 3 min

Payment certificates and variations (South Africa, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

Start task 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Fictional project
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
Work in the ERP
5 tasks, about 2 h 45 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillTask 1
    • Contract instruction CI 03Task 2
    • Contract Data, guarantee optionTask 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Task 4
    • Draft for the second certificateTask 5
YouQuantity surveyor for the employer

Goes from you

    • Remeasured quantities and the adjustmentTask 1
    • Variation order for CI 03Task 2
    • Payment reduction and its releaseTask 3
    • Interim payment certificate 1Task 4
    • Certificate 2 with VATTask 5
    Principal agentSigns what you value

Your route through the job

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Task 1 · 35 min

    Remeasure the provisional items

    You produce
    Remeasured rock and fill, and the adjustment to the bill
    Document
    Joint site records, bill preamble
    In the ERP
    Bill of Quantities
  2. Value the changes

    Task 2 · 30 min

    Price a contract instruction

    You produce
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Document
    Contract instruction CI 03 and the bill rates
    In the ERP
    Variations
  3. Set the reduction

    Task 3 · 30 min

    The payment reduction and its release

    You produce
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Document
    Contract Data D 1.0 and the forecast
    In the ERP
    Contracts
  4. Certify

    Task 4 · 35 min

    Interim payment certificate 1

    You produce
    Interim payment certificate 1, net amount certified
    Document
    Progress and the materials list
    In the ERP
    Contracts
  5. Certify

    Task 5 · 35 min

    Certificate 2: do not pay the bricks twice

    You produce
    Certificate 2: what the draft overclaims, amount due with VAT
    Document
    Contractor's draft for 25 May
    In the ERP
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Task 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Task 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Task 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Task 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Task 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Blue is what the task adds; grey is carried over from before.

In short. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.