Betalingssertifikater og endringer (Sør-Afrika, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Fiktivt prosjekt- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Arbeid i ERP
- 5 oppgaver, omtrent 2 t 45 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillOppgave 1
- Contract instruction CI 03Oppgave 2
- Contract Data, guarantee optionOppgave 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Oppgave 4
- Draft for the second certificateOppgave 5
Går fra deg
- Remeasured quantities and the adjustmentOppgave 1
- Variation order for CI 03Oppgave 2
- Payment reduction and its releaseOppgave 3
- Interim payment certificate 1Oppgave 4
- Certificate 2 with VATOppgave 5
Din vei gjennom prosjektet
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Oppgave 1 · 35 min
Mål om de foreløpige postene
- Du leverer
- Remeasured rock and fill, and the adjustment to the bill
- Dokument
- Joint site records, bill preamble
- I ERP
- Bill of Quantities
Value the changes
Oppgave 2 · 30 min
Prisfastsett en kontraktsinstruks
- Du leverer
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Dokument
- Contract instruction CI 03 and the bill rates
- I ERP
- Variations
Set the reduction
Oppgave 3 · 30 min
Betalingsreduksjonen og frigivelsen av den
- Du leverer
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Dokument
- Contract Data D 1.0 and the forecast
- I ERP
- Contracts
Certify
Oppgave 4 · 35 min
Betalingssertifikat 1
- Du leverer
- Interim payment certificate 1, net amount certified
- Dokument
- Progress and the materials list
- I ERP
- Contracts
Certify
Oppgave 5 · 35 min
Sertifikat 2: ikke betal for teglet to ganger
- Du leverer
- Certificate 2: what the draft overclaims, amount due with VAT
- Dokument
- Contractor's draft for 25 May
- I ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.