Εισαγωγή στο μάθημα · 3 λ.
Πιστοποιητικά πληρωμής και μεταβολές (Νότια Αφρική, JBCC)
You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.
Φανταστικό έργο- Building
- Single-storey community clinic of 620 m², load-bearing brick walls
- Contract
- JBCC Principal Building Agreement, edition 6.2, with bills of quantities
- Currency
- Rand, certificates with VAT
- Εργασία στο ERP
- 5 εργασίες, περίπου 2 ώ. 45 λ.
Ποιος δίνει τι σε ποιον
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Έρχεται σε εσάς
- Principal agentIssues instructions and certificates
- Joint site records of rock and fillΕργασία 1
- Contract instruction CI 03Εργασία 2
- Contract Data, guarantee optionΕργασία 3
- Building contractorContractor, is paid on the certificates
- Materials on site for claim 1Εργασία 4
- Draft for the second certificateΕργασία 5
Φεύγει από εσάς
- Remeasured quantities and the adjustmentΕργασία 1
- Variation order for CI 03Εργασία 2
- Payment reduction and its releaseΕργασία 3
- Interim payment certificate 1Εργασία 4
- Certificate 2 with VATΕργασία 5
Η διαδρομή σας στο έργο
Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.
Value the changes
Εργασία 1 · 35 λ.
Επανεπιμέτρηση των προσωρινών στοιχείων
- Παράγετε
- Remeasured rock and fill, and the adjustment to the bill
- Έγγραφο
- Joint site records, bill preamble
- Στο ERP
- Bill of Quantities
Value the changes
Εργασία 2 · 30 λ.
Τιμολόγηση εντολής σύμβασης (contract instruction)
- Παράγετε
- Contract instruction CI 03 valued by clause 26.2 and recorded
- Έγγραφο
- Contract instruction CI 03 and the bill rates
- Στο ERP
- Variations
Set the reduction
Εργασία 3 · 30 λ.
Η μείωση πληρωμής και η αποδέσμευσή της
- Παράγετε
- The payment reduction (a share held back as a guarantee) and its release at practical completion
- Έγγραφο
- Contract Data D 1.0 and the forecast
- Στο ERP
- Contracts
Certify
Εργασία 4 · 35 λ.
Ενδιάμεσο πιστοποιητικό πληρωμής 1
- Παράγετε
- Interim payment certificate 1, net amount certified
- Έγγραφο
- Progress and the materials list
- Στο ERP
- Contracts
Certify
Εργασία 5 · 35 λ.
Πιστοποιητικό 2: μην πληρώσετε τα τούβλα δύο φορές
- Παράγετε
- Certificate 2: what the draft overclaims, amount due with VAT
- Έγγραφο
- Contractor's draft for 25 May
- Στο ERP
- Contracts
From the bill to the amount due
Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.
Με μπλε ό,τι προσθέτει η εργασία· με γκρι ό,τι έρχεται από πριν.
Με λίγα λόγια. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.