Introducere în curs · 3 min

Certificate de plată și variații (Africa de Sud, JBCC)

You are the quantity surveyor for the employer (the client) on a community clinic: you value the builder's work so that the principal agent, who runs the contract for the client, can certify payment. In five tasks under the JBCC Principal Building Agreement, South Africa's standard building contract, you remeasure the work below ground, price a contract instruction, set the payment reduction and prepare two interim payment certificates.

Începe sarcina 1

A white single-storey clinic with a pitched roof and a ladder against its porch, mounds of excavated earth in front of a low white wall, and a site cabin to the left.Proiect fictiv
Umthombo Community ClinicWalls up, earth heaped in front
Building
Single-storey community clinic of 620 m², load-bearing brick walls
Contract
JBCC Principal Building Agreement, edition 6.2, with bills of quantities
Currency
Rand, certificates with VAT
Lucru în ERP
5 sarcini, circa 2 h 45 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Principal agentIssues instructions and certificates
    • Joint site records of rock and fillSarcina 1
    • Contract instruction CI 03Sarcina 2
    • Contract Data, guarantee optionSarcina 3
  • Building contractorContractor, is paid on the certificates
    • Materials on site for claim 1Sarcina 4
    • Draft for the second certificateSarcina 5
TuQuantity surveyor for the employer

Pleacă de la tine

    • Remeasured quantities and the adjustmentSarcina 1
    • Variation order for CI 03Sarcina 2
    • Payment reduction and its releaseSarcina 3
    • Interim payment certificate 1Sarcina 4
    • Certificate 2 with VATSarcina 5
    Principal agentSigns what you value

Traseul tău prin proiect

Three tasks fix what the contract sum is made of, two turn it into certificates. Start with task 1: in the Bill of Quantities you replace the estimated rock and fill with what was measured on site.

  1. Value the changes

    Sarcina 1 · 35 min

    Remăsurarea articolelor provizorii

    Produci
    Remeasured rock and fill, and the adjustment to the bill
    Document
    Joint site records, bill preamble
    În ERP
    Bill of Quantities
  2. Value the changes

    Sarcina 2 · 30 min

    Evaluarea unei instrucțiuni contractuale

    Produci
    Contract instruction CI 03 valued by clause 26.2 and recorded
    Document
    Contract instruction CI 03 and the bill rates
    În ERP
    Variations
  3. Set the reduction

    Sarcina 3 · 30 min

    Reducerea de plată și eliberarea ei

    Produci
    The payment reduction (a share held back as a guarantee) and its release at practical completion
    Document
    Contract Data D 1.0 and the forecast
    În ERP
    Contracts
  4. Certify

    Sarcina 4 · 35 min

    Certificatul de plată interimar 1

    Produci
    Interim payment certificate 1, net amount certified
    Document
    Progress and the materials list
    În ERP
    Contracts
  5. Certify

    Sarcina 5 · 35 min

    Certificatul 2: nu plăti cărămizile de două ori

    Produci
    Certificate 2: what the draft overclaims, amount due with VAT
    Document
    Contractor's draft for 25 May
    În ERP
    Contracts

From the bill to the amount due

Each step adds one rule to what the employer owes. Value is cumulative, so every certificate restarts from the whole.

Provisional estimate, omittedMeasured provisional workFirm bill items
Sarcina 1Measure what was builtProvisional items, estimates made before anyone could see the ground, are taken out and replaced by the quantity measured on site: rock as it lay, fill as compacted.
Instruction, by ruleMeasured provisional workFirm bill items
Sarcina 2Value an instructionClause 26.2 gives an order: a bill rate if the work is the same, a rate adjusted for similar work, and cost plus a margin for what the bill does not have.
Payment reductionValue certified
Sarcina 3Hold back the reductionA share of every certificate is withheld as the guarantee's payment reduction. At practical completion the held sum is released.
Payment reductionMaterials that do not qualifyQualifying materialsWork to date
Sarcina 4Certificate 1Work to date plus only the materials that qualify: on site, protected and insured. Stock at a yard without a guarantee waits.
VATPayment reductionCertified beforeWork to date, cumulative
Sarcina 5Certificate 2The whole value to date, less what was certified before. Materials now built into the walls are work, not paid again. VAT goes on at the end.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Measure what was built. Value by the order of clause 26.2. Hold the reduction. Pay a material once, and cumulative less last time.